1/27/2023: Work accomplished this week…
- Continue MEP rough ins in DOH Kitchen.
- Continue wall layout and framing in DOH Kitchen.
- Completed roof trusses at new electrical room.
- Began installing roofing system at new electrical room addition.
- Excavated, installed, and backfilled new electrical vault for main service lines.
- Began MEP rough ins in Bistro.
1/20/2023:Work accomplished this week…
- Continue MEP rough ins in DOH Kitchen.
- Continue wall layout and framing in DOH Kitchen.
- Set roof trusses at new electrical room.
- Completed underground rough-in in Bistro.
- Continue demolition of exterior façade at Bistro.
1/6/2023: Work accomplished this week…
- Completed saw cutting in Bistro Area.
- Began removing concrete slab in Bistro Area.
- Completed MEP demolition in Bistro Area
- Prepped and placed concrete slab in new electrical room.
- Began layout of MEP in DOH Kitchen.
- Began wall layout and framing in DOH Kitchen.
- Continued exterior excavation/installation of new underground electrical/telecom conduit.
- Set grease trap.
12/30/2022: Work accomplished this week…
– Continued MEP demolition in Bistro Area.
– Started saw cutting in Bistro Area for new underground rough ins
– Continued exterior excavation for new underground telecom lines
– Poured concrete slab in DOH kitchen
12/22/2022: Work accomplished this week…
– Began installing floor drains/troughs in lower level kitchen area (DOH kitchen).
– Prep concrete slab in lower level kitchen area (DOH kitchen) and new electrical room.
– Continue demolition in Bistro Area.
– Continue exterior excavation for new underground telecom lines.
– Completed trenching for new grease trap.
12/16/2022: Work accomplished this week…
– Completed running conduit for new electrical services in DOH Kitchen.
– Continued demolition in Bistro Area.
– Began exterior excavation for new underground telecom lines.
10/17/2022: Construction has begun! We will post updates regularly, so check back here frequently to see what’s new!