View our progress by clicking here!
5/26/2023: Work accomplished this week…
North Wing
- Complete installation of building pad vapor barrier and interior footers/haunches rebar in preparation for placing concrete slab.
- Begin installation of metal pan stairs in stair tower #2.
South Wing
- Continue excavation and installation of underground plumbing.
- Continue excavation and installation of sanitary sewer manhole and piping between SSMH-1 and SSMH-2.
- Continue applying waterproofing membrane and perimeter underground insulation at newly placed foundation walls.
- Begin forming and placing concrete foundation for stair tower #1.
Lower Level – Commons
- Completed installation of MEP finishes.
- Continue installing kitchen equipment.
- Continue installation of outdoor mechanical equipment.
Upper Level – Commons
- Continue MEP rough-ins.
- Completed framing within mailroom.
- Began hanging and finishing drywall in mailroom.
- Continue MEP rough-ins in mailroom.
- Began installation of new rooftop units.
5/19/2023: Work accomplished this week…
North Wing
- Continue excavation for interior concrete footers, haunches and underground utility lines.
- Continue installing underground plumbing lines.
South Wing
- Complete excavation, installing rebar, and placing concrete for building foundation.
- Began excavation and installation of electrical underground conduit.
- Began masonry foundation work along west and east run of building.
- Began applying waterproofing membrane, perimeter underground insulation and foundation drains at south foundation walls.
Lower Level – Commons
- Continue installation of MEP finishes.
- Began installing kitchen equipment.
- Completed painting work within new electrical room.
- Began installation of outdoor mechanical equipment.
Upper Level – Commons
- Continue MEP rough-ins.
- Completed insulating and hanging/finishing drywall within new IT Closet.
- Began installation of ceiling grid.
- Continue framing within mailroom.
- Began MEP rough-ins in mailroom.
5/12/2023: Work accomplished this week…
North Wing
- Continue excavation for interior concrete footers, haunches, and underground utility lines.
- Continue installing underground plumbing lines and electrical conduit.
South Wing
- Continue excavation, installing rebar, and placing concrete for building foundation.
Lower Level – Commons
- Completed installation of ceiling grid.
- Completed MEP rough-ins.
- Began installation of MEP finishes.
- Began installing perimeter ceiling tile.
- Began painting work within new electrical room.
Upper Level – Commons
- Continue MEP rough-ins.
- Completed installing roofing system above new IT Closet.
- Completed applying 1st coat of paint on drywall ceilings and walls.
- Began framing walls within existing mailroom.
5/5/2023: Work accomplished this week…
North Wing
- Continue excavation for interior concrete footers, haunches, and underground utility lines.
- Continue installing underground plumbing lines and electrical conduit.
- Completed excavation and installation of west side stormwater structures A.7 to A.9 and associated piping.
South Wing
- Completed preparing building pad.
- Completed forming and placing concrete for south foundation retaining wall.
- Continue excavation, installing rebar, and placing concrete for building foundation.
- Completed excavation and installation of water line to building.
Lower Level – Commons
- Continue installation of ceiling grid.
- Continue MEP rough-ins.
- Completed hanging and finishing drywall in electrical room.
- Began painting door frames.
Upper Level – Commons
- Continue MEP rough-ins.
- Completed hanging and finishing drywall soffits.
- Completed installing wood trusses for new IT closet.
- Continue replacing mechanical finishes in main corridor and lobby areas ceilings.
- Began painting drywall ceilings and walls.
- Completed demolition of existing mailroom.
4/28/2023: Work accomplished this week…
North Wing
- Continue excavation for interior concrete footers, haunches, and underground plumbing lines.
- Continue installing underground plumbing lines.
- Began excavation and installation of west side stormwater structures and piping.
- Began installing underground conduit for secondary electrical lines.
South Wing
- Continue preparing building pad.
- Continue excavation, installing rebar, and placing concrete for building foundation.
Lower Level
- Began installation of ceiling grid.
- Continue MEP rough-ins.
- Completed new interior gas piping work.
- Began hanging and finishing drywall in electrical room.
Upper Level
- Continue MEP rough-ins.
- Continue hanging and finishing drywall soffits.
- Completed framing and sheathing for new IT closet.
- Began installing wood trusses for new IT closet.
- Continue replacing mechanical finishes in main corridor and lobby areas ceilings.
- Relocated mailroom to temporary location.
4/21/2023: Work accomplished this week…
North Wing
- Completed laying masonry walls at elevator #1.
- Completed installing perimeter underground insulation, applying waterproofing membrane, and foundation drains.
- Began excavation for interior concrete footers, haunches, and underground plumbing lines.
- Began installing underground plumbing lines.
South Wing
- Continue preparing building pad.
- Began excavation, installing rebar, and placing concrete for building foundation.
Lower Level-Commons
- Completed resinous flooring installation.
- Continued new interior gas piping work.
Upper Level-Commons
- Continued MEP rough-ins.
- Completed framing soffits at coffee shop.
- Continued hanging and finishing drywall.
- Completed preparing former library space to be converted into a temporary mail room.
- Began framing for new IT closet.
- Began replacing mechanical finishes in main corridor and lobby areas ceilings.
4/14/2023: Work accomplished this week…
- Continue preparing south wing building pad.
- Completed masonry foundation work along south run of north wing of the building.
- Completed laying masonry walls at elevator shaft #2.
- Began laying masonry walls at elevator shaft #1.
- Continue installing perimeter underground insulation, applying waterproofing membrane, and foundation drains around exterior of building.
- Completed installing retaining wall railings.
Lower Level – Commons
- Continued MEP rough-ins in kitchen.
- Completed insulating mechanical ductwork.
- Completed hanging FRP.
- Continued new interior gas piping work.
- Completed hanging fan coil units.
Upper Level – Commons
- Continued MEP rough-ins.
- Continued framing soffits.
- Continued hanging and finishing drywall.
- Formed and placed concrete slab on grade at connector.
- Continued preparing former library space to be converted into a temporary mail room.
4/7/2023: Work accomplished this week…
- Continue preparing south wing building pad.
- Completed laying masonry walls at stair tower #2.
- Continue masonry foundation work along south run of north wing of the building.
- Began laying masonry walls at elevator shafts.
- Began installing perimeter underground insulation, applying waterproofing membrane, and foundation drains around exterior of building.
- Completed installing retaining wall.
- Completed running primary underground electrical conduit.
Lower Level-Commons
- Continued MEP rough-ins in kitchen.
- Continued insulating mechanical ductwork.
- Continued hanging FRP.
- Continued new interior gas piping work.
- Began hanging fan coil units.
Upper Level-Commons
- Continued MEP rough-ins.
- Continued framing soffits.
- Continued hanging and finishing drywall.
- Completed laying masonry foundation block, rigid insulation, and waterproofing at Bistro connector.
- Completed running underground conduit to new IT closet.
- Continued preparing former library space to be converted into a temporary mail room.
3/31/2023: Work accomplished this week…
- Continue preparing south wing building pad.
- Completed laying masonry foundation at stair tower #2 and along west, north, and east run of north wing of building.
- Began laying masonry walls at stair tower #2.
- Began masonry foundation work along south run of north wing of the building.
- Began forming and placing concrete piers.
- Completed installing rebar, forming walls, and placing concrete at elevator shafts.
- Began applying waterproofing membrane around exterior of building and elevator shafts.
- Continue installing retaining wall.
- Continue running primary underground electrical conduit.
Lower Level-Commons
- Continued Continued insulating mechanical ductwork.
- Completed installing exhaust hoods and walk-in refrigerators.
- Continued hanging FRP.
- Began new interior gas piping work
Upper Level-Commons
- Continued MEP rough-ins.
- Continued hanging and finishing drywall.
- Complete laying masonry foundation block at Bistro Connector.
- Continued running underground conduit to new IT closet.
- Began preparing former library space to be converted into a temporary mail room.
3/24/2023: Work accomplished this week…
- Continue preparing south wing building pad.
- Completed exterior concrete foundation work along north, east, and south run of north wing of building.
- Began laying masonry foundation work at stair tower #2 and along north and west run of north wing of building.
- Began installing rebar, forming walls, and placing concrete at elevator shafts.
- Completed excavating and installing gas line for Commons Building.
- Began installing retaining wall.
- Began running primary underground electrical conduit.
Lower Level-Commons
- Continued MEP rough-ins in kitchen & electrical room.
- Continued insulating mechanical ductwork.
- Completed exterior brick work.
- Continued installing exhaust hoods and walk-in refrigerators.
- Began hanging FRP.
- Set new gas meter.
Upper Level-Commons
- Continued MEP rough-ins.
- Continued insulating and hanging drywall.
- Completed installing wood clad windows.
- Began laying masonry foundation block at Bistro Connector.
- Continued running underground conduit to new IT closet.
3/17/2023: Work accomplished this week…
- Completed installation of east side stormwater structure A.5 and associated piping to structure A.4.
- Continue preparing site for building pad.
- Began excavation, installing rebar, and placing concrete at exterior foundations along north side of building and at elevator #2 pit.
- Began excavating and installing gas line for Commons Building.
Lower Level-Commons
- Continued MEP rough-ins in kitchen & electrical room.
- Continued insulating mechanical ductwork.
- Continued exterior brick work.
- Completed installing exterior siding at electrical room.
- Completed installing kitchen exhaust fans.
- Began installing exhaust hoods and walk-in refrigerators
Upper Level-Commons
- Continued MEP rough-ins.
- Began insulating and hanging drywall.
- Began preparing openings for new window installation.
- Began laying out masonry foundation block for connector.
- Began running underground conduit to new IT closet.
3/10/2023: Work accomplished this week…
- Completed installation of east side stormwater structures A.3 and A.4 and associated piping.
- Began installation of east side stormwater structure A.5 and associated piping to structure A.4.
- Continue preparing site for building pad.
- Completed bulk excavation for new retaining wall.
- Continue tying rebar in preparation for foundation work to begin.
Commons-Lower Level
- Continued MEP rough-ins in kitchen & electrical room.
- Continued insulating mechanical ductwork.
- Continued insulating and hanging cement board.
- Began exterior brick work.
- Started installing kitchen exhaust fans
- Placed concrete housekeeping pad for gas line.
Commons-Upper Level
- Continued MEP rough ins.
- Completed soffit and wall framing.
- Completed excavation and placing concrete footers for Bistro connector.
3/3/2023: Work accomplished this week…
- Continue installation of east side stormwater structures A.3 and A.4 and associated piping.
- Connect to existing stormwater in Bluebird Lane.
- Install wet tap to connect existing water line into new water line.
- Continue preparing site for building pad.
- Began bulk excavation for new retaining wall.
- Began tying rebar in preparation for foundation work to begin.
Commons- Lower Level
- Continued MEP rough-ins in kitchen & electrical room.
- Began insulating mechanical ductwork.
- Began insulating and hanging cement board.
Commons-Upper Level
- Continued soffit and wall framing.
- Continued MEP rough ins.
- Continue excavation and placing concrete footers for Bistro connector.
- Completed installing new flooring in Gift Shop.
2/17/2023: Work accomplished this week…
- Completed removing parking lot blacktop.
- Began installation of east side stormwater structures and piping.
- Installed sanitary manhole 5 and piping to grease trap.
- Continued MEP rough ins in kitchen & electrical room.
- Began removing masonry block for new mechanical openings.
- Installed steel lintels for new mechanical openings.
- Began coring through upper floor deck for new floor drains.
- Continued soffit and wall framing.
- Continued MEP rough ins.
- Completed shoring existing trusses for new openings to Bistro connector.
- Continue underground rough ins for new IT closet.
2/10/2023: Work accomplished this week…
- Completed stripping and stockpiling topsoil.
- Continue removing parking lot blacktop.
- Completed installing construction entrances.
- Excavation of south wing deep foundation.
- Scanning site for location of existing underground utilities.
- Completed framing and wall blocking (in commons).
- Completed installing roofing system at new electrical room addition (in commons).
- Applied liquid vapor barrier at new electrical room.
1/27/2023: Work accomplished this week…
- Continue MEP rough ins in DOH Kitchen.
- Continue wall layout and framing in DOH Kitchen.
- Completed roof trusses at new electrical room.
- Began installing roofing system at new electrical room addition.
- Excavated, installed, and backfilled new electrical vault for main service lines.
- Began MEP rough ins in Bistro.
1/20/2023:Work accomplished this week…
- Continue MEP rough ins in DOH Kitchen.
- Continue wall layout and framing in DOH Kitchen.
- Set roof trusses at new electrical room.
- Completed underground rough-in in Bistro.
- Continue demolition of exterior façade at Bistro.
1/6/2023: Work accomplished this week…
- Completed saw cutting in Bistro Area.
- Began removing concrete slab in Bistro Area.
- Completed MEP demolition in Bistro Area
- Prepped and placed concrete slab in new electrical room.
- Began layout of MEP in DOH Kitchen.
- Began wall layout and framing in DOH Kitchen.
- Continued exterior excavation/installation of new underground electrical/telecom conduit.
- Set grease trap.
12/30/2022: Work accomplished this week…
- Continued MEP demolition in Bistro Area.
- Started saw cutting in Bistro Area for new underground rough ins
- Continued exterior excavation for new underground telecom lines
- Poured concrete slab in DOH kitchen
12/22/2022: Work accomplished this week…
- Began installing floor drains/troughs in lower level kitchen area (DOH kitchen).
- Prep concrete slab in lower level kitchen area (DOH kitchen) and new electrical room.
- Continue demolition in Bistro Area.
- Continue exterior excavation for new underground telecom lines.
- Completed trenching for new grease trap.
12/16/2022: Work accomplished this week…
- Completed running conduit for new electrical services in DOH Kitchen.
- Continued demolition in Bistro Area.
- Began exterior excavation for new underground telecom lines.
10/17/2022: Construction has begun! We will post updates regularly, so check back here frequently to see what’s new!