View our progress by clicking here!
11/17/2023: Work accomplished this week…
North Wing
- Continued balcony framing around perimeter of building.
- Continued MEP rough-ins on upper floors.
- Continued installation of Duxxbak decking.
- Completed connecting condensate lines and roof drains into underground storm lines.
- Continue insulating walls and ceilings in first floor units and along corridor.
- Began hanging and finishing drywall within units and along corridor.
- Continue exterior vinyl siding installation.
- Began installation of stone veneer siding.
South Wing
- Completed installation of roof trusses.
- Began installation of roof decking.
COMMONS:
Lower-Level Office Space
- Continue re-working of ceiling grid.
- Began insulating walls and hanging drywall.
Upper-Level
- Continue framing soffits in formal dining room.
- Completed framing walls within kitchen space.
- Continue MEP rough-ins.
- Completed framing walls and hanging cement board around fireplace in existing lobby area.
- Began excavation for new IL Apartment connector foundation.
New Connector
- Completed applying exterior EIFS system.
11/10/2023: Work accomplished this week…
North Wing
- Continued balcony framing around perimeter of building.
- Continued MEP rough-ins on all floors.
- Continued installation of Duxxbak decking.
- Continued connecting condensate lines and roof drains into underground storm lines.
- Began insulating walls along corridor.
- Began insulating walls and ceilings within units.
- Began hanging ceiling hat track within resident units.
- Began installation of exterior vinyl siding.
South Wing
- Completed installation of 4th floor wall panels.
- Began installation of roof trusses.
Commons: Lower-Level Maintenance Shop
- Completed framing walls.
- Began re-working of ceiling grid.
Upper-Level
- Continue framing soffits in formal dining room.
- Continue framing walls within kitchen space.
- Continue MEP rough-ins in formal dining room.
New Connector
- Began applying exterior EIFS system.
- Continue WCC pre-punchlist work.
11/3/2023: Work accomplished this week…
North Wing
- Continued balcony framing and completed window installation around perimeter of building.
- Continued MEP rough-ins on all floors.
- Continued installation of Duxxbak decking.
- Completed installation of TPO roofing system.
- Began connecting condensate lines and roof drains into underground storm lines.
- Began spray foam insulation at building band boards.
South Wing
- Completed installation of 3rd floor wall panels.
- Completed installation of 4th floor joists and decking.
- Began installation of 4th floor wall panels.
Lower-Level Maintenance Shop
- Completed remediation of flooring.
- Installed door frames.
- Began framing walls.
Upper-Level
- Continue framing soffits in formal dining room.
- Began framing walls within kitchen space.
- Continue MEP rough-ins in formal dining room.
- Completed demolition of men’s and women’s bathroom.
New Connector
- Completed laying brick veneer on exterior south side façade.
- Continue WCC pre-punchlist work.
10/27/2023: Work accomplished this week…
North Wing
- Continued balcony framing and window installation around perimeter of building.
- Continued MEP rough-ins on all floors.
- Completed installation of patio doors on 1st floor.
- Continued installation of Duxxbak decking.
- Began installation of TPO roofing system.
- Began applying stone veneer siding.
South Wing
- Completed installation of 3rd floor joists and decking.
- Began installation of 3rd floor wall panels.
Upper Level
- Completed demolition work within formal dining room.
- Completed demolition work within kitchen space.
- Began framing soffits and ceilings in formal dining room.
- Began MEP rough-ins in formal dining room.
- Completed punchlist work at lounge, meeting room, and unisex bathroom.
New Connector
- Completed priming and painting walls and soffits.
- Completed laying brick veneer on exterior north side façade.
- Completed installation of trim work including chair rail and handrail.
- Began WCC pre-punchlist work.
10/20/2023: Work accomplished this week…
North Wing
- Continued balcony framing and window installation around perimeter of building.
- Completed installation of shingle roofing system.
- Completed laying CMU columns at east canopy area.
- Continued MEP rough-ins on all floors.
- Began installation of patio doors.
- Continue installation of Duxxbak decking.
South Wing
- Completed setting structural steel.
- Completed installation of 1st floor wall panels.
- Completed installation of 2nd floor joists and decking.
- Began installation of 2nd floor wall panels.
Upper Level – Commons
- Continued demolition work within formal dining room.
- Continued demolition work within kitchen space.
- Began wall and soffit layout in formal dining room.
- Began WCC pre-punchlist work in lounge, meeting room, and unisex bathroom.
New Connector
- Completed hanging and finishing drywall.
- Completed laying custom carpet.
- Completed MEP rough-in work.
- Began priming and painting walls and soffits.
- Began laying brick veneer on exterior façade.
10/13/2023: Work accomplished this week…
North Wing
- Completed laying roof sheathing.
- Continued balcony framing around perimeter of building.
- Continued MEP rough-ins on first, second, third floors.
- Continued installation of windows around perimeter of building.
- Continued installation of shingle roofing system.
- Began laying CMU columns at east canopy area.
South Wing
- Prepared and placed concrete building pad.
- Began setting structural steel.
- Began installation of first floor wall panels.
Upper Level – Commons
- Continued painting soffits along corridor.
- Continued demolition work within formal dining room.
- Began demolition work within kitchen space.
- Set countertop within unisex bathroom and lounge area.
New Connector
- Completed installation of windows and storefront.
- Completed installation of roofing system.
- Completed insulating walls and ceilings.
- Began hanging and finishing drywall.
- Continued installation of MEP rough-ins.
- Applied waterproof membrane on exterior.
10/6/2023: Work accomplished this week…
North Wing
- Completed setting roof trusses.
- Continued laying roof sheathing.
- Continued balcony framing around perimeter of building.
- Continued MEP rough-ins on first, second, third floors.
- Continued installation of windows around perimeter of building.
- Completed laying CMU block for entry pavilion walls.
- Completed setting stair tower metal door frames.
- Begin installation of shingle roofing system.
South Wing
- Completed underground plumbing.
- Excavated for interior footers and haunches.
Commons
- Completed prepping wall for paint application.
- Continued priming and painting walls and soffits along corridor.
- Completed removal of existing flooring along corridor and replacing it with new carpet/LVT.
- Completed installation of unisex bathroom floor and= wall tile.
- Installed casework within unisex bathroom.
- Completed installing MEP finishes within unisex bathroom, lounge space, and meeting room 210.
- Continued demolition work within formal dining room.
- Completed framing walls and installing roof trusses and sheathing at new connector.
- Began MEP rough-ins and installation of windows at new connector.
9/29/2023: Work accomplished this week…
North Wing
- Continued setting roof trusses and sheathing.
- Continued balcony framing around perimeter of building.
- Continued MEP rough-ins on first and second floors.
- Began MEP rough-ins on third floor.
- Began installation of windows on west side of building
- Began laying CMU block for entry pavilion walls.
- Began setting stair tower metal door frames.
South Wing
- Set steel column anchor plates in concrete footers.
Commons
- Completed design team’s punchlist work in Bistro.
- Continued removal of existing wallpaper along corridor and prepping wall for paint application.
- Continued priming and painting walls and soffits along corridor.
- Began removal of existing flooring along corridor and replacing it with new carpet/LVT.
- Installed casework within lounge area.
- Set unisex bathroom floor and wall tile.
- Continued demolition work within formal dining room.
- Completed laying CMU fire wall at new connector.
- Began framing walls for new connector.
9/22/2023: Work accomplished this week…
North Wing
- Continued setting roof trusses and sheathing.
- Continued balcony framing along Bluebird Lane and south side of building.
- Continued MEP rough-ins on first and second floors.
- Continued hanging pre-rock along main corridor ceiling.
- Prepped and placed first floor concrete patio floors.
South Wing
- Completed installation of underground plumbing lines.
Commons
- Items on order to complete design team’s punchlist work in Bistro.
- Continued removal of existing wallpaper along corridor and prepping wall for paint application.
- Continued priming and painting walls and soffits along corridor.
- Prepped and placed concrete slab and began laying CMU fire wall at Bistro connector.
- Completed hanging temporary walls around formal dining room.
- Began demolition work within formal dining room.
9/15/2023: Work accomplished this week…
North Wing
- Completed installation of fourth floor wall panels.
- Begin setting of roof trusses.
- Continued balcony framing along Bluebird Lane and south side of building.
- Continued MEP rough-ins on first and second floors.
- Completed framing and hanging vertical duct shaft linear outside of stair tower #2.
- Continued hanging pre-rock along main corridor ceiling.
- Began installation of exterior windows.
South Wing
- Completed laying and grouting CMU foundation block.
- Completed applying underground waterproofing system.
Upper Level – Commons
- Items on order to complete design team’s punchlist work in Bistro.
- Completed hanging and finishing drywall at unisex bathroom, lounge space and meeting room 210.
- Began priming and painting walls in available spaces.
- Completed MEP rough-ins at unisex bathroom, lounge spaces and meeting room 210.
- Continued removal of existing wallpaper along main corridor and prepping wall for paint application.
- Completed placing masonry foundation block, waterproofing and insulation for Bistro connector.
9/8/2023: Work accomplished this week…
North Wing
- Continued installation of fourth floor wall panels.
- Continued balcony framing along Bluebird Lane.
- Began excavation for balcony foundations along south side of building.
- Continued MEP rough-ins on first floor.
- Began hanging pre-rock along main corridor ceiling.
South Wing
- Completed excavation of west side perimeter foundation.
- Placed concrete perimeter foundation and began laying masonry block along west side.
Lower Level – Commons
- Passed Department of Health Inspection.
Upper Level – Commons
- Continued design team’s punchlist work in Bistro.
- Continued to hang and finish drywall at unisex bathroom/lounge spaces.
- Continued MEP rough-ins at unisex bathroom/lounge spaces.
- Began removal of existing wallpaper along main corridor and prepping wall for paint application.
- Formed and placed Bistro connector foundation.
- Began placing masonry foundation block for Bistro connector.
9/1/2023: Work accomplished this week…
North Wing
- Completed installation of fourth floor joists and decking.
- Began installation of fourth floor wall panels.
- Continued balcony framing along Bluebird Lane.
- Began MEP rough-ins on first floor.
- Base paved west parking lot.
- Prepped and place concrete for west side patio stairs and ramp.
- Began hanging pre-rock in shower and tub openings.
- Completed installation of storm line between structures A.6 and A.7.
- Completed excavation of east side entrance way piers, installed rebar, and placed concrete.
South Wing
- Completed demolition of south vaults, duct bank and deactivated underground utilities.
Lower Level – Commons
- Completed start-up of kitchen equipment.
Upper Level – Commons
- Continued design team’s punchlist work in Bistro.
- Completed framing and insulating walls and began hanging drywall at unisex bathroom/lounge spaces.
- Continued MEP rough-ins at unisex bathroom/lounge spaces.
- Completed demolition of existing link.
8/25/2023: Work accomplished this week…
North Wing
- Completed installation of third floor wall panels.
- Began installation of fourth floor joists.
- Installed third floor structural steel.
- Continued second floor wood framing punch work.
- Continued balcony framing along Bluebird Lane.
- Began layout for plumbing rough-ins.
South Wing
- Continued demolition of south vaults, duct bank and deactivated underground utilities.
- Placed concrete in metal pan stairs in stair tower #1.
- Placed concrete pad in sprinkler room.
Lower Level – Commons
- Completed start-up of mechanical equipment
- Continue start-up of kitchen equipment.
- Completed testing and balancing of equipment.
Upper Level – Commons
- Continued design team’s punchlist work in Bistro.
- Completed setting ceramic wall tile on pizza oven.
- Set furniture within Fast Casual seating area and meeting room.
- Began framing of walls and MEP rough-ins at unisex bathroom/lounge spaces.
- Continued demolition of existing link.
- Completed painting corridor 241 walls.
8/18/2023: Work accomplished this week…
North Wing
- Completed installation of third floor decking.
- Continue installation of third floor wall panels.
- Completed first floor wood framing punch work.
- Began second floor wood framing punch work.
- Began first floor balcony framing.
- Completed placing concrete curbing at west parking lot.
- Connected building sanitary line into site sanitary line.
South Wing
- Completed underground plumbing within sprinkler room.
- Completed installation of new communication lines.
- Began demolition of south vaults, duct bank and deactivated underground utilities.
- Connect SSMH-4 into SSMH-3.
- Framed stair tower #1 interior walls.
Lower Level – Commons
- Completed design team’s punchlist work.
- Continued start-up of kitchen/mechanical equipment.
Upper Level – Commons
- Began design team’s punchlist work in Bistro.
- Installed decorative metal at pizza oven.
- Completed demolition work at future lounge/unisex bathroom spaces.
- Began demolition of existing link.
- Began painting corridor 241 walls.
8/11/2023: Work accomplished this week…
North Wing
- Completed installing third floor wood joists.
- Began installation of third floor decking.
- Began installation of third floor wall panels.
- Began first floor wood framing punch work.
- Began placing concrete curbing at west parking lot.
South Wing
- Continue installation of new communication lines.
- Completed installing pan stairs at stair tower #1.
- Began backfilling sprinkler room floor cavity.
- Continue backfilling around south walls.
Lower Level – Commons
- Continued architect punch list work.
- Began start-up of kitchen/mechanical equipment.
- Installed walk-off carpet and base in mechanical corridor.
Upper Level – Commons
- Removed temporary walls at Bistro/Coffee Shop.
- Installed temporary walls and began demolition at future lounge/unisex bathroom spaces.
- Completed installation of new storefront doors in Bistro.
- Completed final connections to food service equipment.
- Began installation of decorative metal panels.
8/4/2023: Work accomplished this week…
North Wing
- Completed installation of second floor wall panels.
- Began installing third floor wood joists.
- Removed forms and began backfilling at west patio ramp walls.
- Installed temporary lighting along first floor corridor.
South Wing
- Completed power switchover.
- Continued installation of new communication lines.
- Continued installing pan stairs at stair tower #1.
- Poured remaining balance of south concrete walls.
- Poured sprinkler room concrete walls.
Lower Level – Commons
- Complete architect punch list work.
- Begin food service equipment start-up.
- Test exhaust hood fire suppression system.
Upper Level – Commons
- Demolish temporary mailroom.
- Begin erecting temporary walls at future lounge/unisex bathroom spaces.
- Complete installation of Bistro countertops and food= service equipment.
- Complete MEP connections to food service equipment.
- Install decorative metal around pizza oven.
- Complete installation of new storefront doors in Bistro.
7/28/2023: Work accomplished this week…
North Wing
- Completed installation of underground basin structure and associated storm structures.
- Installed stormwater line across Blue Bird Lane adjacent to newly installed underground basin.
- Completed installation of first floor wall panels and second floor joists.
- Installed first floor structural steel.
- Began installing second floor decking and wall panels.
- Formed and poured west patio ramp walls.
South Wing
- Continued running new communication and power lines.
- Began installation of pan stairs in stair tower #1.
Lower Level – Commons
- Continued architect punch list work.
- Finished installing temporary breakers.
- Installed ceiling grid and tile in service elevator lobby.
Upper Level – Commons
- Began installing ceiling grid and tile in Bistro.
- Continued installation of casework in Bistro.
- Continued installation of food service equipment.
- Completed punch list work in mailroom and removed temporary wall.
- Began installation of MEP finishes in Bistro.
7/21/2023: Work accomplished this week…
North Wing
- Continued installation of underground basin structure and associated storm structures.
- Continued framing first floor walls.
- Installed first floor structural steel.
- Began placing wood joists and second floor decking.
South Wing
- Continued running new communication and power lines.
- Continued backfilling around south walls.
Lower Level – Commons
- Continued architect punchlist work.
- Continued installation of electrical panel breakers.
- Installed epoxy flooring at service elevator lobby.
- Installed vinyl flooring in mechanical corridor.
Upper Level – Commons
- Installed carpeting in meeting room.
- Installed wall covering and decorative light fixtures in Bistro and meeting room.
- Continued installation of casework in Bistro and Coffee Shop.
- Began installation of food service equipment in Bistro.
- Completed installation of baseboard and began installing pilaster panels in Bistro.
- Installed mailroom island casework.
- Installed countertop in package room.
7/14/2023: Work accomplished this week…
North Wing
- Placed stone at underground basin structure.
- Placed west side concrete ramp and patio foundation.
- Poured concrete in pan stairs in stair tower #2.
- Began 1st floor wood wall framing.
South Wing
- Continued running new communication and power lines.
- Continued backfilling around south walls.
- Completed installation of underground gas line.
Lower Level – Commons
- Continued architect punchlist work.
- Continued installation of electrical panel breakers.
- Installed FRP at service elevator landing.
- Installed air hoods at walk-in coolers.
Upper Level – Commons
- Completed installation of pantry casework.
- Began installation of Grill and Coffee Shop casework.
- Installed flooring in Coffee Shop area and corridor.
- Continued installation of trim in Bistro and Coffee Shop.
- Completed installation of trim in mailroom.
- Began pilaster installation in mailroom.
7/7/2023: Work accomplished this week…
North Wing
- Completed excavation work for underground basin and began installation of liner.
- Completed excavation for west side patio foundation and placed concrete mud sill.
- Framed interior center wall of stair tower #2.
- Installed storm structure A.9 and continued excavation and associated piping to structure A.11.
South Wing
- Continued running new communication and power lines.
- Continued backfilling around south walls.
Lower Level – Commons
- Continue architect punchlist work.
- Completed installation of food service equipment.
- Continue installation of electrical panel breakers.
Upper Level – Commons
- Completed installation of wood baseboard and crown molding within mailroom.
- Completed installation of crown molding at Coffee Shop ceiling.
- Completed installation of flooring in package room.
- Accepted delivery of pantry casework.
6/30/23: Work accomplished this week…
North Wing
- Continued excavation work for underground basin.
- Completed installing vapor barrier, rebar, and placing concrete building pad west of stair tower #2.
- Placed concrete on steel decking at top of elevator and stair towers.
- Graded and stoned east side parking lot.
South Wing
- Continued running new communication and power lines.
Lower Level – Commons
- Continue installation of electrical panels.
- Continue installation of remaining food service equipment.
- Began architect punchlist work.
- Completed abatement work within maintenance corridor.
Upper Level – Commons
- Completed installing exhaust duct to pizza oven and overhead exhaust hood.
- Continued installation of stained wood trim and crown molding in mailroom and Coffee Shop area.
- Installed ceiling grid and painted walls within package room.
- Completed laying flooring within mailroom and Bistro area
6/22/2023: Work accomplished this week…
North Wing
- Completed installation of metal stairs in stair tower #2.
- Began installing storm structures on west side parking lot that are to connect into underground basin.
- Completed laying masonry block for elevator tower #2.
- Completed underground plumbing/electrical work west of elevator tower #2 and prepared area for slab pour.
- Completed installation of metal decking atop of stair tower #2 and elevator towers #1 and #2.
South Wing
- Placed concrete building pad south of elevator #1 to corridor 124.
- Continued running new communication and power lines.
Lower Level – Commons
- Continue installation of electrical panels.
- Began installation of remaining food service equipment.
- Continue Wohlsen pre-punchlist work.
Upper Level – Commons
- Began installing exhaust duct to pizza oven and overhead exhaust hood.
- Completed MEP finishes in Bistro seating area.
- Completed installation of wood ceilings in Bistro and Coffee Shop area.
- Began installation of stained wood trim and crown molding in mailroom.
- Completed installation of MEP finishes in mailroom.
6/16/2023: Work accomplished this week…
North Wing
- Continued installation of metal stairs in stair tower #2.
- Continued preparation work for underground basin on west side of construction site.
- Began laying masonry block for elevator tower #2.
- Completed installation of conduit along Bluebird Lane for communication lines.
South Wing
- Completed excavation and installation of underground plumbing lines and electrical/low voltage conduit.
- Completed preparation work to pour building slab south of elevator tower #1 to corridor 124.
- Completed east run of exterior masonry foundation.
- Began running new communication lines.
Lower Level – Commons
- Completed installation of outdoor mechanical equipment.
- Continue installation of electrical panels and switchgear.
- Began Wohlsen pre-punchlist work.
Upper Level – Commons
- Completed installation of new rooftop units.
- Continued MEP rough-ins in Bistro.
- Continued MEP finishes in Bistro seating area.
- Continued installation of wood ceilings in Bistro.
- Completed installation of mailboxes.
- Completed installation of ceiling grid within mailroom.
- Began installation of MEP finishes in mailroom.
- Completed installation of underground conduit under existing connector.
6/9/2023: Work accomplished this week…
North Wing
- Completed installing vapor barrier and rebar for concrete building pad.
- Poured concrete building pad east of stair tower #2.
- Continued installation of metal stairs in stair tower #2.
- Continued preparation work for underground basin on west side of construction site.
South Wing
- Continue excavation and installation of underground plumbing lines and electrical/low voltage conduit.
- Completed laying masonry block for stair tower #1.
- Continue to backfill behind south foundation wall.
Lower Level-Commons
- Continue installation of outdoor mechanical equipment.
- Began installation of electrical panels and switchgear.
Upper Level-Commons
- Continued MEP rough-ins in Bistro.
- Continued MEP finishes in Bistro seating area.
- Completed installation of ceiling grid in Bistro.
- Completed hanging and finishing drywall in mailroom.
- Completed painting work in IT closet and mailroom.
- Continued installation of new rooftop units.
- Began installation of wood ceilings in Bistro.
- Began installation of mailboxes.
6/2/2023: Work accomplished this week…
North Wing
- Continue installing vapor barrier in preparation of rebar install and placing of concrete building pad.
- Began installation of building pad rebar.
- Began installation of metal stairs in stair tower #2.
- Began preparation work for underground basin on west side of construction site.
South Wing
- Continue excavation and installation of underground plumbing.
- Completed excavation and installation of sanitary sewer manholes and piping between SSMH 1 and SSMH-3.
- Completed excavation and placing concrete for stair tower #1 foundation.
- Began laying masonry block for stair tower #1.
Lower Level – Commons
- Completed installing kitchen equipment.
- Continued installation of outdoor mechanical equipment.
Upper Level – Commons
- Continued MEP rough-ins in Bistro.
- Began MEP finishes in Bistro seating area.
- Began installation of ceiling grid in Bistro seating area.
- Completed resinous flooring installation in Bistro.
- Completed installation of windowsills in Bistro.
- Continued hanging and finishing drywall in mailroom.
- Completed MEP rough-ins in mailroom.
- Began painting work in IT closet and mailroom.
- Continued installation of new rooftop units.
5/26/2023: Work accomplished this week…
North Wing
- Complete installation of building pad vapor barrier and interior footers/haunches rebar in preparation for placing concrete slab.
- Begin installation of metal pan stairs in stair tower #2.
South Wing
- Continue excavation and installation of underground plumbing.
- Continue excavation and installation of sanitary sewer manhole and piping between SSMH-1 and SSMH-2.
- Continue applying waterproofing membrane and perimeter underground insulation at newly placed foundation walls.
- Begin forming and placing concrete foundation for stair tower #1.
Lower Level – Commons
- Completed installation of MEP finishes.
- Continue installing kitchen equipment.
- Continue installation of outdoor mechanical equipment.
Upper Level – Commons
- Continue MEP rough-ins.
- Completed framing within mailroom.
- Began hanging and finishing drywall in mailroom.
- Continue MEP rough-ins in mailroom.
- Began installation of new rooftop units.
5/19/2023: Work accomplished this week…
North Wing
- Continue excavation for interior concrete footers, haunches and underground utility lines.
- Continue installing underground plumbing lines.
South Wing
- Complete excavation, installing rebar, and placing concrete for building foundation.
- Began excavation and installation of electrical underground conduit.
- Began masonry foundation work along west and east run of building.
- Began applying waterproofing membrane, perimeter underground insulation and foundation drains at south foundation walls.
Lower Level – Commons
- Continue installation of MEP finishes.
- Began installing kitchen equipment.
- Completed painting work within new electrical room.
- Began installation of outdoor mechanical equipment.
Upper Level – Commons
- Continue MEP rough-ins.
- Completed insulating and hanging/finishing drywall within new IT Closet.
- Began installation of ceiling grid.
- Continue framing within mailroom.
- Began MEP rough-ins in mailroom.
5/12/2023: Work accomplished this week…
North Wing
- Continue excavation for interior concrete footers, haunches, and underground utility lines.
- Continue installing underground plumbing lines and electrical conduit.
South Wing
- Continue excavation, installing rebar, and placing concrete for building foundation.
Lower Level – Commons
- Completed installation of ceiling grid.
- Completed MEP rough-ins.
- Began installation of MEP finishes.
- Began installing perimeter ceiling tile.
- Began painting work within new electrical room.
Upper Level – Commons
- Continue MEP rough-ins.
- Completed installing roofing system above new IT Closet.
- Completed applying 1st coat of paint on drywall ceilings and walls.
- Began framing walls within existing mailroom.
5/5/2023: Work accomplished this week…
North Wing
- Continue excavation for interior concrete footers, haunches, and underground utility lines.
- Continue installing underground plumbing lines and electrical conduit.
- Completed excavation and installation of west side stormwater structures A.7 to A.9 and associated piping.
South Wing
- Completed preparing building pad.
- Completed forming and placing concrete for south foundation retaining wall.
- Continue excavation, installing rebar, and placing concrete for building foundation.
- Completed excavation and installation of water line to building.
Lower Level – Commons
- Continue installation of ceiling grid.
- Continue MEP rough-ins.
- Completed hanging and finishing drywall in electrical room.
- Began painting door frames.
Upper Level – Commons
- Continue MEP rough-ins.
- Completed hanging and finishing drywall soffits.
- Completed installing wood trusses for new IT closet.
- Continue replacing mechanical finishes in main corridor and lobby areas ceilings.
- Began painting drywall ceilings and walls.
- Completed demolition of existing mailroom.
4/28/2023: Work accomplished this week…
North Wing
- Continue excavation for interior concrete footers, haunches, and underground plumbing lines.
- Continue installing underground plumbing lines.
- Began excavation and installation of west side stormwater structures and piping.
- Began installing underground conduit for secondary electrical lines.
South Wing
- Continue preparing building pad.
- Continue excavation, installing rebar, and placing concrete for building foundation.
Lower Level
- Began installation of ceiling grid.
- Continue MEP rough-ins.
- Completed new interior gas piping work.
- Began hanging and finishing drywall in electrical room.
Upper Level
- Continue MEP rough-ins.
- Continue hanging and finishing drywall soffits.
- Completed framing and sheathing for new IT closet.
- Began installing wood trusses for new IT closet.
- Continue replacing mechanical finishes in main corridor and lobby areas ceilings.
- Relocated mailroom to temporary location.
4/21/2023: Work accomplished this week…
North Wing
- Completed laying masonry walls at elevator #1.
- Completed installing perimeter underground insulation, applying waterproofing membrane, and foundation drains.
- Began excavation for interior concrete footers, haunches, and underground plumbing lines.
- Began installing underground plumbing lines.
South Wing
- Continue preparing building pad.
- Began excavation, installing rebar, and placing concrete for building foundation.
Lower Level-Commons
- Completed resinous flooring installation.
- Continued new interior gas piping work.
Upper Level-Commons
- Continued MEP rough-ins.
- Completed framing soffits at coffee shop.
- Continued hanging and finishing drywall.
- Completed preparing former library space to be converted into a temporary mail room.
- Began framing for new IT closet.
- Began replacing mechanical finishes in main corridor and lobby areas ceilings.
4/14/2023: Work accomplished this week…
- Continue preparing south wing building pad.
- Completed masonry foundation work along south run of north wing of the building.
- Completed laying masonry walls at elevator shaft #2.
- Began laying masonry walls at elevator shaft #1.
- Continue installing perimeter underground insulation, applying waterproofing membrane, and foundation drains around exterior of building.
- Completed installing retaining wall railings.
Lower Level – Commons
- Continued MEP rough-ins in kitchen.
- Completed insulating mechanical ductwork.
- Completed hanging FRP.
- Continued new interior gas piping work.
- Completed hanging fan coil units.
Upper Level – Commons
- Continued MEP rough-ins.
- Continued framing soffits.
- Continued hanging and finishing drywall.
- Formed and placed concrete slab on grade at connector.
- Continued preparing former library space to be converted into a temporary mail room.
4/7/2023: Work accomplished this week…
- Continue preparing south wing building pad.
- Completed laying masonry walls at stair tower #2.
- Continue masonry foundation work along south run of north wing of the building.
- Began laying masonry walls at elevator shafts.
- Began installing perimeter underground insulation, applying waterproofing membrane, and foundation drains around exterior of building.
- Completed installing retaining wall.
- Completed running primary underground electrical conduit.
Lower Level-Commons
- Continued MEP rough-ins in kitchen.
- Continued insulating mechanical ductwork.
- Continued hanging FRP.
- Continued new interior gas piping work.
- Began hanging fan coil units.
Upper Level-Commons
- Continued MEP rough-ins.
- Continued framing soffits.
- Continued hanging and finishing drywall.
- Completed laying masonry foundation block, rigid insulation, and waterproofing at Bistro connector.
- Completed running underground conduit to new IT closet.
- Continued preparing former library space to be converted into a temporary mail room.
3/31/2023: Work accomplished this week…
- Continue preparing south wing building pad.
- Completed laying masonry foundation at stair tower #2 and along west, north, and east run of north wing of building.
- Began laying masonry walls at stair tower #2.
- Began masonry foundation work along south run of north wing of the building.
- Began forming and placing concrete piers.
- Completed installing rebar, forming walls, and placing concrete at elevator shafts.
- Began applying waterproofing membrane around exterior of building and elevator shafts.
- Continue installing retaining wall.
- Continue running primary underground electrical conduit.
Lower Level-Commons
- Continued Continued insulating mechanical ductwork.
- Completed installing exhaust hoods and walk-in refrigerators.
- Continued hanging FRP.
- Began new interior gas piping work
Upper Level-Commons
- Continued MEP rough-ins.
- Continued hanging and finishing drywall.
- Complete laying masonry foundation block at Bistro Connector.
- Continued running underground conduit to new IT closet.
- Began preparing former library space to be converted into a temporary mail room.
3/24/2023: Work accomplished this week…
- Continue preparing south wing building pad.
- Completed exterior concrete foundation work along north, east, and south run of north wing of building.
- Began laying masonry foundation work at stair tower #2 and along north and west run of north wing of building.
- Began installing rebar, forming walls, and placing concrete at elevator shafts.
- Completed excavating and installing gas line for Commons Building.
- Began installing retaining wall.
- Began running primary underground electrical conduit.
Lower Level-Commons
- Continued MEP rough-ins in kitchen & electrical room.
- Continued insulating mechanical ductwork.
- Completed exterior brick work.
- Continued installing exhaust hoods and walk-in refrigerators.
- Began hanging FRP.
- Set new gas meter.
Upper Level-Commons
- Continued MEP rough-ins.
- Continued insulating and hanging drywall.
- Completed installing wood clad windows.
- Began laying masonry foundation block at Bistro Connector.
- Continued running underground conduit to new IT closet.
3/17/2023: Work accomplished this week…
- Completed installation of east side stormwater structure A.5 and associated piping to structure A.4.
- Continue preparing site for building pad.
- Began excavation, installing rebar, and placing concrete at exterior foundations along north side of building and at elevator #2 pit.
- Began excavating and installing gas line for Commons Building.
Lower Level-Commons
- Continued MEP rough-ins in kitchen & electrical room.
- Continued insulating mechanical ductwork.
- Continued exterior brick work.
- Completed installing exterior siding at electrical room.
- Completed installing kitchen exhaust fans.
- Began installing exhaust hoods and walk-in refrigerators
Upper Level-Commons
- Continued MEP rough-ins.
- Began insulating and hanging drywall.
- Began preparing openings for new window installation.
- Began laying out masonry foundation block for connector.
- Began running underground conduit to new IT closet.
3/10/2023: Work accomplished this week…
- Completed installation of east side stormwater structures A.3 and A.4 and associated piping.
- Began installation of east side stormwater structure A.5 and associated piping to structure A.4.
- Continue preparing site for building pad.
- Completed bulk excavation for new retaining wall.
- Continue tying rebar in preparation for foundation work to begin.
Commons-Lower Level
- Continued MEP rough-ins in kitchen & electrical room.
- Continued insulating mechanical ductwork.
- Continued insulating and hanging cement board.
- Began exterior brick work.
- Started installing kitchen exhaust fans
- Placed concrete housekeeping pad for gas line.
Commons-Upper Level
- Continued MEP rough ins.
- Completed soffit and wall framing.
- Completed excavation and placing concrete footers for Bistro connector.
3/3/2023: Work accomplished this week…
- Continue installation of east side stormwater structures A.3 and A.4 and associated piping.
- Connect to existing stormwater in Bluebird Lane.
- Install wet tap to connect existing water line into new water line.
- Continue preparing site for building pad.
- Began bulk excavation for new retaining wall.
- Began tying rebar in preparation for foundation work to begin.
Commons- Lower Level
- Continued MEP rough-ins in kitchen & electrical room.
- Began insulating mechanical ductwork.
- Began insulating and hanging cement board.
Commons-Upper Level
- Continued soffit and wall framing.
- Continued MEP rough ins.
- Continue excavation and placing concrete footers for Bistro connector.
- Completed installing new flooring in Gift Shop.
2/17/2023: Work accomplished this week…
- Completed removing parking lot blacktop.
- Began installation of east side stormwater structures and piping.
- Installed sanitary manhole 5 and piping to grease trap.
- Continued MEP rough ins in kitchen & electrical room.
- Began removing masonry block for new mechanical openings.
- Installed steel lintels for new mechanical openings.
- Began coring through upper floor deck for new floor drains.
- Continued soffit and wall framing.
- Continued MEP rough ins.
- Completed shoring existing trusses for new openings to Bistro connector.
- Continue underground rough ins for new IT closet.
2/10/2023: Work accomplished this week…
- Completed stripping and stockpiling topsoil.
- Continue removing parking lot blacktop.
- Completed installing construction entrances.
- Excavation of south wing deep foundation.
- Scanning site for location of existing underground utilities.
- Completed framing and wall blocking (in commons).
- Completed installing roofing system at new electrical room addition (in commons).
- Applied liquid vapor barrier at new electrical room.
1/27/2023: Work accomplished this week…
- Continue MEP rough ins in DOH Kitchen.
- Continue wall layout and framing in DOH Kitchen.
- Completed roof trusses at new electrical room.
- Began installing roofing system at new electrical room addition.
- Excavated, installed, and backfilled new electrical vault for main service lines.
- Began MEP rough ins in Bistro.
1/20/2023:Work accomplished this week…
- Continue MEP rough ins in DOH Kitchen.
- Continue wall layout and framing in DOH Kitchen.
- Set roof trusses at new electrical room.
- Completed underground rough-in in Bistro.
- Continue demolition of exterior façade at Bistro.
1/6/2023: Work accomplished this week…
- Completed saw cutting in Bistro Area.
- Began removing concrete slab in Bistro Area.
- Completed MEP demolition in Bistro Area
- Prepped and placed concrete slab in new electrical room.
- Began layout of MEP in DOH Kitchen.
- Began wall layout and framing in DOH Kitchen.
- Continued exterior excavation/installation of new underground electrical/telecom conduit.
- Set grease trap.
12/30/2022: Work accomplished this week…
- Continued MEP demolition in Bistro Area.
- Started saw cutting in Bistro Area for new underground rough ins
- Continued exterior excavation for new underground telecom lines
- Poured concrete slab in DOH kitchen
12/22/2022: Work accomplished this week…
- Began installing floor drains/troughs in lower level kitchen area (DOH kitchen).
- Prep concrete slab in lower level kitchen area (DOH kitchen) and new electrical room.
- Continue demolition in Bistro Area.
- Continue exterior excavation for new underground telecom lines.
- Completed trenching for new grease trap.
12/16/2022: Work accomplished this week…
- Completed running conduit for new electrical services in DOH Kitchen.
- Continued demolition in Bistro Area.
- Began exterior excavation for new underground telecom lines.
10/17/2022: Construction has begun! We will post updates regularly, so check back here frequently to see what’s new!