Luther Crest Construction Updates:

View our progress by clicking here!

4/19/2024: Work accomplished this week…
North Wing

  • Completed MEP rough-ins on upper floors.
  • Continued priming and painting walls/ceilings within units and corridors.
  • Continued MEP finishes within third and fourth floor units.
  • Began installation of MEP finishes in corridors.
  • Continued installation of resident unit casework and countertops within fourth floor units.
  • Continued laying flooring on fourth floor.
  • Continued installation of west side elevator.
  • Began installation of ceiling grid on third and fourth floor corridors.
  • Continued installation of corridor pilaster panels and chair rail.
  • Began grading west side parking lot area.

South Wing

  • Continued hanging and finishing drywall throughout.
  • Continued priming and painting walls/ceilings within units and corridors.
  • Continued MEP rough-ins throughout.
  • Continued installation of pre-hung doors trim, casework, and countertops within units.
  • Framed soffits and poured gypcrete floor at new connector.

Commons

  • Completed finishing drywall soffits and walls in the upper-level link corridor to the new IL apartment.
  • Completed installation of LVP flooring and painting of walls and ceilings in the upper-level link corridor to the new IL apartment.
  • Continued architectural and SCOPOS punchlist for formal dining and bar area.
  • Completed hanging drywall and ceiling grid/tile within lower-level link corridor to new IL apartment.
  • Completed installation of furniture within upper-level areas.

 

4/12/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued priming and painting walls/ceilings within units and corridors.
  • Continued MEP finishes within third and fourth floor units.
  • Continued installation of resident unit casework and countertops within third and fourth floor units.
  • Continued laying flooring on fourth floor.
  • Continued installation of west side elevator.
  • Began installation of ceiling grid on second floor corridor.
  • Completed priming and painting west side stairwell.
  • Completed installation of west side storefront entrances.
  • Began installation of corridor pilaster panels on second floor.

South Wing

  • Continued hanging and finishing drywall throughout.
  • Began priming and painting walls/ceilings within units and corridors.
  • Continued MEP rough-ins throughout.
  • Continued installation of pre-hung doors trim, casework, and countertops within units.
  • Set sprinkler pump and exterior building generators.
  • Completed hanging drywall along connector to Commons Building.
  • Began pouring curb line on east side parking lot.

Commons

  • Completed installation of MEP finishes.
  • Completed installation of food service equipment and casework.
  • Continued finishing drywall soffits and walls in new IL apartment connector.
  • Completed painting within formal dining and bar area.
  • Completed installation of carpet and LVP flooring.
  • Installed motorized window shades.
  • Began architectural and SCOPOS punchlist for formal dining and bar area.
  • Began hanging drywall and ceiling grid within lowerlevel link corridor to new IL apartment.

 

 

4/5/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued finishing drywall soffits along corridors.
  • Continued priming and painting walls/ceilings within units and corridors.
  • Continued MEP finishes within third and fourth floor units.
  • Continued installation of resident unit casework, countertops, pre-hung doors, and trim within third and fourth floor units.
  • Continued laying flooring on third and fourth floors.
  • Completed installation of metal roof at east side entry pavilion.
  • Completed installation of west side elevator.
  • Continued installation of balcony railings.
  • Began installation of ceiling grid on first floor corridor.
  • Began priming and painting west side stairwell.
  • Began installation of west side storefront entrances.

South Wing

  • Continued hanging and finishing drywall throughout.
  • Continued MEP rough-ins throughout.
  • Continued installation of balcony railings.
  • Continued pulling wire to sub panels.
  • Continued installation of pre-hung doors and trim within second, third, and fourth floor units.
  • Began forming exterior concrete generator pad.

Commons

  • Continued installation of MEP finishes.
  • Continued installation of food service equipment and casework.
  • Continued hanging and finishing drywall soffits and walls in new IL apartment connector.
  • Continued painting within formal dining and bar areas.
  • Completed installation of acoustical panel ceilings.
  • Completed installation of millwork finishes in Fullenbach Room.
  • Completed installation of exterior brick veneer.
  • Completed installation of interior/exterior storefront windows.
  • Began installation of carpet and LVP flooring.
  • Began installation of fireplace tile.
  • Completed installation of lounge wallpaper.

 

 

3/29/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins on upper floors.
  • Completed finishing drywall within first floor corridor and commons spaces.
  • Began framing, hanging, and finishing drywall soffits along corridors on upper floors.
  • Continued priming and painting walls/ceilings within units on upper floors.
  • Continued MEP finishes within second and third floor units.
  • Continued installation of resident unit casework, countertops, pre-hung doors, and trim within third and fourth floor units.
  • Continued laying flooring on upper floors.
  • Continued installation of balcony railings.
  • Continued installation of metal roof at east side entry pavilion.
  • Began installation of west side elevator.

South Wing

  • Continued hanging and finishing drywall throughout.
  • Continued MEP rough-ins throughout.
  • Continued installation of balcony railings.
  • Completed framing, sheathing and installation of windows at new IL Apartment connector.
  • Completed installation of switchgear and continued pulling wire to sub panels.
  • Continued installation of pre-hung doors and trim within second, third, and fourth floor units.

Commons

  • Continued installation of MEP finishes.
  • Continued installation of food service equipment and casework.
  • Completed installation of roofing system and framing walls/soffits for new IL apartment connector.
  • Completed priming and painting ceilings within Fullenbach room and at Captain’s table.
  • Completed MEP rough-ins within new IL apartment connector.
  • Completed installation of bar ceramic tile.
  • Continued priming and painting metal doors and frames.
  • Began installation of acoustical panel ceilings.
  • Completed waterproofing exterior of new IL apartment connector.
  • Began installation of millwork finishes in Fullenbach Room.

 

3/22/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued finishing drywall within first floor common space and along first floor corridor ceilings.
  • Continued priming and painting walls/ceilings within units on upper floors.
  • Continued MEP finishes within second and third floor units.
  • Continued installation of resident unit casework, countertops, pre-hung doors, and trim within third and fourth floor units.
  • Continued laying flooring on upper floors.
  • Continued installation of balcony railings.
  • Continued installation of metal roof at east side entry pavilion.

South Wing

  • Continued hanging and finishing drywall throughout.
  • Continued MEP rough-ins throughout.
  • Continued installation of balcony railings.
  • Completed setting structural steel and began framing/sheathing new Common’s Building connector.
  • Continued installation of switchgear and pulling wire to sub panels.
  • Began installation of pre-hung doors and trim within third and fourth floor units.
  • Poured gypcrete on second floor.

Commons

  • Continued installation of MEP finishes.
  • Continued installation of food service equipment and casework.
  • Completed setting roof trusses and began installing roofing system for new IL apartment connector.
  • Completed hanging drywall ceiling in Fullenbach Room and at Captain’s table.
  • Began priming and painting ceilings within Fullenbach room and at Captain’s table.
  • Began framing walls and soffits in IL apartment connector.
  • Continued installation of bar area ceramic tile.
  • Installed ACT grid in expo kitchen.
  • Completed installation of dishwasher exhaust fan.
  • Began priming and painting metal doors and frames.

 

3/15/2024: Work accomplished this week…

North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued finishing drywall within first floor common space and along first floor corridor ceilings.
  • Continued priming and painting walls/ceilings within units on upper floors.
  • Continued MEP finishes within second and third floor units.
  • Continued installation of resident unit casework, pre-hung doors, and trim within third and fourth floor units.
  • Continued setting countertops on third floor.
  • Continued installation of exterior façade.
  • Continued laying flooring within second and third floor units.
  • Continued installation of balcony railings.
  • Continued installation of metal roof at east side entry pavilion.
  • Began installation of elevators.

South Wing

  • Continued hanging and finishing drywall throughout.
  • Continued MEP rough-ins throughout.
  • Continued installation of balcony railings.
  • Began setting structural steel for new Common’s Building connector.
  • Began setting switchgear and exterior transformer vault.

Commons

  • Continued installation of MEP finishes.
  • Continued installation of food service equipment and casework.
  • Completed installation of exhaust fan duct to expo kitchen hood.
  • Continued setting roof trusses for new IL apartment connector.
  • Began hanging drywall ceiling in Fullenbach Room and at Captain’s table.
  • Began installation of bar area ceramic tile.

 

3/8/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins on upper floors.
  • Began hanging and finishing drywall within first floor common space and along first floor corridor ceilings.
  • Continued priming and painting walls/ceilings within units on upper floors.
  • Continued MEP finishes within second and third floor units.
  • Continued installation of resident unit casework, pre-hung doors, and trim within third and fourth floor units.
  • Set countertops on second and third floor unit casework.
  • Continued installation of exterior façade.
  • Continued laying flooring within second and third floor units.
  • Continued installation of balcony railings.
  • Began installation of metal roof at east side entry pavilion.
  • Began setting apartment entrance metal frames and doors on upper floors.

South Wing

  • Continued hanging and finishing drywall on upper floors.
  • Continued MEP rough-ins throughout.
  • Formed and placed new connector slab on grade.
  • Continued installation of balcony railings.
  • Poured gypcrete on third floor.

Commons

  • Continued installation of MEP finishes.
  • Continued installation of food service equipment and casework.
  • Completed installation of MUA-2 ductwork.
  • Continued installation of exhaust fan ducting to expo kitchen hood.
  • Completed hanging cement board at fireplace.
  • Completed framing opening within formal dining area into new IL apartment connector.
  • Began setting roof trusses for new IL apartment connector.
  • Set doors and frames within kitchen area.

 

2/23/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued hanging and finishing drywall and framing soffits on third and fourth floors.
  • Continued priming and painting walls/ceilings within units on third floor.
  • Continued MEP finishes within first and second floor units.
  • Continued installation of resident unit casework, pre-hung doors, and trim within third and fourth floor units.
  • Set countertops on second floor unit casework.
  • Continued installation of exterior façade.
  • Continued laying flooring within first and second floor units.
  • Continued installation of balcony railings.

South Wing

  • Completed insulating walls and ceilings on second floor.
  • Continued hanging and finishing drywall on second and third floors.
  • Continued MEP rough-ins throughout.
  • Began forming footers/walls for new connector to Commons building.
  • Began installation of balcony railings.
  • Began pouring gypcrete on fourth floor.

Commons

  • Continued installation of MEP finishes.
  • Continued installation of food service equipment and casework.
  • Continued final coating walls and ceilings.
  • Continued millwork installation within bar and formal dining area.
  • Completed framing fireplace surround and began hanging cement board.
  • Completed infilling flooring sections within corridors.
  • Began framing opening within formal dining area into new IL apartment connector.
  • Completed installation of tile floor within Fullenbach Room.

 

2/16/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued hanging and finishing drywall and framing soffits on third and fourth floors.
  • Continued priming and painting walls/ceilings within units on third floor.
  • Continued MEP finishes within first and second floor units.
  • Continued installation of resident unit casework, pre-hung doors, and trim within third and fourth floor units.
  • Continued installation of exterior façade.
  • Continued laying flooring within first and second floor units.
  • Continued installation of balcony railings.

South Wing

  • Completed insulating walls and ceilings on third floor.
  • Continued hanging and finishing drywall on third and fourth floors.
  • Continued MEP rough-ins throughout.
  • Began backfilling around footers/walls for new connector to Commons building.

Commons

  • Completed finishing drywall ceiling within formal dining room and bar area.
  • Continued installation of MEP finishes.
  • Continued installation of food service equipment.
  • Began installation of food service casework.
  • Continued final coating walls and ceilings.
  • Began millwork installation within bar and formal dining area.
  • Began framing fireplace surround.
  • Began infilling flooring sections within corridors.

 

 

2/9/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued hanging and finishing drywall and framing soffits on upper floors.
  • Continued priming and painting walls/ceilings within units on second and third floors.
  • Continued MEP finishes within first floor units.
  • Continued installation of resident unit casework, pre-hung doors, and trim within second and third floor units.
  • Continued installation of exterior façade.
  • Continued laying flooring within first floor units.
  • Set rooftop mechanical equipment.
  • Installed window blinds within first floor units.
  • Poured fourth floor gypcrete underlayment.
  • Began installation of balcony railings.

South Wing

  • Began insulating walls and ceilings on fourth and third floors.
  • Began hanging and finishing drywall on fourth floor.
  • Continued MEP rough-ins throughout.
  • Formed and poured concrete footers/walls for new connector to Commons building.

Commons

  • Continued finishing drywall ceiling within formal dining room and bar area.
  • Continued installation of MEP finishes.
  • Continued installation of food service equipment.
  • Began final coating walls and ceilings.
  • Completed CMU block at IL apartment connector.
  • Completed installation of millwork outside of men’s and women’s bathrooms.
  • Completed repair work within Bedford connector.

 

2/2/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued hanging and finishing drywall within units and along corridors on all floors.
  • Continued framing and hanging drywall soffits along second floor corridor.
  • Continued priming and painting walls/ceilings within units on second floor.
  • Continued MEP finishes within first floor units.
  • Continued installation of resident unit casework in second floor units.
  • Continued installation of pre-hung doors and door trim in third floors.
  • Continued installation of exterior façade.
  • Began laying flooring with first floor units.

South Wing

  • Continued MEP rough-ins throughout.
  • Tied rebar and place concrete for new connector foundation to Commons building.

Commons

  • Continued finishing drywall within formal dining room and bar area.
  • Completed hanging wood slat ceilings within formal dining area.
  • Continued installation of MEP finishes.
  • Continued installation of interior storefront windows.
  • Began installation of food service equipment.
  • Began CMU block at IL apartment connector.
  • Completed installation of ceiling grid within staging kitchen.
  • Began installation of millwork outside of men’s and women’s bathrooms.
  • Began repair work within Bedford connector.

 

1/26/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued hanging and finishing drywall within units andalong corridors on all floors.
  • Continued framing and hanging drywall soffits along second floor corridor.
  • Continued priming and painting walls/ceilings within units on first and second floor.
  • Completed pouring third floor gypcrete.
  • Began MEP finishes within first floor units.
  • Completed installation of countertops in units 101 thru 104.
  • Continued installation of resident unit casework.
  • Continued installation of pre-hung doors and door trim in second floor units
  • Continued installation of exterior façade.

South Wing

  • Continued MEP rough-ins throughout.
  • Completed installation of gas piping.
  • Continued excavation for new connector foundation to Commons building.

Commons

  • Continued finishing drywall within formal dining room.
  • Continued hanging wood slat ceilings within formal dining area.
  • Completed MEP rough-ins at bar area.
  • Began installation of MEP finishes.
  • Began installation of interior storefront windows.
  • Completed removal of exterior brick façade.
  • Completed saw cutting and block work at new opening on lower level for IL apartment connector.

 

1/19/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued hanging and finishing drywall within units and along corridors on all floors.
  • Began framing and hanging drywall soffits along first floor corridor.
  • Continued priming and painting walls/ceilings within units on first and second floor.
  • Continued installation of resident unit casework.
  • Began installation of pre-hung doors and door trim in second floor units
  • Completed installation of main water line along first floor corridor.
  • Completed waterproofing balcony decks above conditioned spaces.
  • Continued installation of exterior façade.

South Wing

  • Continued MEP rough-ins throughout.
  • Completed installation of patio doors.
  • Began installation of gas piping.
  • Began excavation for new connector foundation to Commons building.

Commons

  • Continue finishing drywall within formal dining room and bar area.
  • Completed installation of resinous flooring within staging kitchen areas.
  • Began hanging wood slat ceilings within formal dining area.
  • Continued MEP rough-ins at bar area.
  • Poured concrete on deck and began backfilling around perimeter of new IL apartment connector.
  • Began saw cutting new opening on lower level at new IL apartment connector.

 

1/12/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued insulating walls and ceilings within units and along corridors on third and fourth floors.
  • Continued hanging and finishing drywall within units and along corridors on second, third, and fourth floors.
  • Continued installation of exterior vinyl and stone veneer siding.
  • Continued priming and painting walls/ceilings within units on first and second floor.
  • Continued installation of resident unit casework.
  • Completed pouring gypcrete underlayment on second floor.
  • Began installation of main water line along first floor corridor.

South Wing

  • Continued MEP rough-ins throughout.
  • Continue installation of patio doors.

Commons

  • Continued finishing drywall within formal dining room and bar area.
  • Began installation of resinous flooring within kitchen areas.
  • Completed installation of ceiling grid within formal dining room.
  • Completed installation of new beer cooler.
  • Continued MEP rough-ins within bar area.
  • Continued priming and painting walls and ceilings within formal dining room.
  • Completed installation of plumbing fixtures within bathrooms.
  • Completed foundational waterproofing on new IL apartment connector.

1/5/2024: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued insulating walls and ceilings within units and along corridors on third floor.
  • Continued hanging and finishing drywall within units and along corridors on second and third floors.
  • Continued installation of exterior vinyl and stone veneer siding.
  • Continue priming walls/ceilings within units for paint application.
  • Began installation of resident unit casework.

South Wing

  • Completed installation of roofing systems.
  • Continued MEP rough-ins throughout.
  • Completed framing balconies and installing Duxxbak decking.
  • Began installation of patio doors.

Commons

  • Continued finishing drywall within formal dining room and bar area.
  • Began installation of FRP walls within kitchen area.
  • Continued MEP rough-ins within bar area.
  • Began priming and painting walls and ceilings within formal dining room.
  • Continued installation of plumbing fixtures within bathrooms.
  • Completed installation of toilet partitions and bathroom accessories.
  • Completed placing concrete walls and began installation of structural steel at new IL apartment connector.

12/22/2023: Work accomplished this week…
North Wing

  • Continued MEP rough-ins throughout.
  • Continued insulating walls and ceilings within units and along corridors on first, second, and third floors.
  • Continued hanging and finishing drywall within units and along corridors on first, second, and third floors.
  • Completed installation of shower and tubs inserts.
  • Continued installation of exterior vinyl and stone veneer siding.
  • Continued installation of pre-hung wood doors and miscellaneous trim work within units.
  • Began priming walls/ceilings within units for paint application.

South Wing

  • Continued installation of roofing systems.
  • Continued MEP rough-ins throughout.
  • Continued framing balconies and installing Duxxbak decking.
  • Completed installation of windows.

Commons

  • Completed hanging cement board within kitchen area.
  • Continued hanging and finishing drywall within formal dining room and bar area.
  • Continued MEP rough-ins within kitchen and bar area.
  • Completed priming and painting walls and ceilings within bathrooms and misc. common spaces.
  • Set countertops within bathrooms.
  • Began installation of plumbing fixtures within bathrooms.
  • Completed flooring installation within commons spaces.

12/15/2023: Work accomplished this week…
North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued insulating walls and ceilings within units and along corridor on first and second floor.
  • Continued hanging and finishing drywall within units and along corridor on first and second floor.
  • Continued installation of shower and tubs inserts.
  • Continued installation of exterior vinyl and stone veneer siding.
  • Continued installation of pre-hung wood doors and miscellaneous trim work within units.
  • Began installation of unit entrance metal doors frames.

South Wing

  • Continued installation of roofing systems.
  • Continued MEP rough-ins on upper floors.
  • Continued framing balconies and installing Duxxbak decking.
  • Continued installation of windows.

Commons – Upper-Level

  • Continued hanging and finishing drywall and cement board within kitchen and formal dining room.
  • Continued MEP rough-ins throughout.
  • Installed new expo kitchen hood and Ansul system cabinet.
  • Completed installation of fireplace quartz surround.
  • Completed installation of floor and wall tile within men’s and women’s bathroom.
  • Set bathroom vanity casework.
  • Completed tying rebar and placing concrete walls for IL apartment connector.

12/8/2023: Work accomplished this week…
North Wing

  • Continued MEP rough-ins on upper floors.
  • Continued insulating walls and ceilings in first and second floor units and along corridors.
  • Continued hanging and finishing drywall within units and along corridor on first floor.
  • Continued installation of shower and tubs inserts.
  • Continued installation of exterior vinyl and stone veneer siding.
  • Began installation of pre-hung wood doors and miscellaneous trim work within units.

South Wing

  • Continued installation of roofing systems.
  • Continued MEP rough-ins on upper floors.
  • Continued framing balconies and installing Duxxbak decking.
  • Began installation of windows.

Commons: Lower-Level Office Space and Corridor

  • Installed new flooring throughout.
  • Primed and painted walls throughout.

Commons: Upper-Level

  • Completed framing walls within kitchen and formal dining room.
  • Began hanging cement board and drywall within kitchen and formal dining room.
  • Continued MEP rough-ins throughout.
  • Completed installation of fireplace tile surround and millwork within lounge area.
  • Began installation of floor and wall tile within men’s and women’s bathroom.
  • Began tying rebar for new concrete walls of IL apartment connector.

12/1/2023: Work accomplished this week…
North Wing

  • Completed balcony framing around perimeter of building.
  • Continued MEP rough-ins on upper floors.
  • Completed installation of Duxxbak decking.
  • Continue insulating walls and ceilings in first and second floor units and along corridors.
  • Continue hanging and finishing drywall within units and along corridor on first floor.
  • Began installation of shower and tubs inserts.
  • Continue installation of exterior vinyl and stone veneer siding.

South Wing

  • Completed installation of roof decking.
  • Began installation of roofing systems.
  • Began MEP rough-ins on first and second floor.
  • Began framing balconies and installing Duxxbak decking.
  • Installed building gas meter.

Commons – Lower-Level Office Space

  • Completed re-working of ceiling grid.
  • Completed hanging and finishing drywall.

Commons – Upper-Level

  • Completed framing soffits in formal dining room.
  • Began framing walls within kitchen and formal dining room.
  • Continue MEP rough-ins throughout.
  • Began installation of fireplace tile surround and millwork within lounge area.
  • Completed hanging drywall and began flooring preparation work within men’s and women’s bathroom.
  • Completed excavation for new IL Apartment connector foundation and placed mud sill.

11/17/2023: Work accomplished this week…
North Wing

  • Continued balcony framing around perimeter of building.
  • Continued MEP rough-ins on upper floors.
  • Continued installation of Duxxbak decking.
  • Completed connecting condensate lines and roof drains into underground storm lines.
  • Continue insulating walls and ceilings in first floor units and along corridor.
  • Began hanging and finishing drywall within units and along corridor.
  • Continue exterior vinyl siding installation.
  • Began installation of stone veneer siding.

South Wing

  • Completed installation of roof trusses.
  • Began installation of roof decking.

COMMONS:

Lower-Level Office Space

  • Continue re-working of ceiling grid.
  • Began insulating walls and hanging drywall.

Upper-Level

  • Continue framing soffits in formal dining room.
  • Completed framing walls within kitchen space.
  • Continue MEP rough-ins.
  • Completed framing walls and hanging cement board around fireplace in existing lobby area.
  • Began excavation for new IL Apartment connector foundation.

New Connector

  • Completed applying exterior EIFS system.

11/10/2023: Work accomplished this week…
North Wing

  • Continued balcony framing around perimeter of building.
  • Continued MEP rough-ins on all floors.
  • Continued installation of Duxxbak decking.
  • Continued connecting condensate lines and roof drains into underground storm lines.
  • Began insulating walls along corridor.
  • Began insulating walls and ceilings within units.
  • Began hanging ceiling hat track within resident units.
  • Began installation of exterior vinyl siding.

South Wing

  • Completed installation of 4th floor wall panels.
  • Began installation of roof trusses.

Commons: Lower-Level Maintenance Shop

  • Completed framing walls.
  • Began re-working of ceiling grid.

Upper-Level

  • Continue framing soffits in formal dining room.
  • Continue framing walls within kitchen space.
  • Continue MEP rough-ins in formal dining room.

New Connector

  • Began applying exterior EIFS system.
  • Continue WCC pre-punchlist work.

11/3/2023: Work accomplished this week…
North Wing

  • Continued balcony framing and completed window installation around perimeter of building.
  • Continued MEP rough-ins on all floors.
  • Continued installation of Duxxbak decking.
  • Completed installation of TPO roofing system.
  • Began connecting condensate lines and roof drains into underground storm lines.
  • Began spray foam insulation at building band boards.

South Wing

  • Completed installation of 3rd floor wall panels.
  • Completed installation of 4th floor joists and decking.
  • Began installation of 4th floor wall panels.

Lower-Level Maintenance Shop

  • Completed remediation of flooring.
  • Installed door frames.
  • Began framing walls.

Upper-Level

  • Continue framing soffits in formal dining room.
  • Began framing walls within kitchen space.
  • Continue MEP rough-ins in formal dining room.
  • Completed demolition of men’s and women’s bathroom.

New Connector

  • Completed laying brick veneer on exterior south side façade.
  • Continue WCC pre-punchlist work.

10/27/2023: Work accomplished this week…
North Wing

  • Continued balcony framing and window installation around perimeter of building.
  • Continued MEP rough-ins on all floors.
  • Completed installation of patio doors on 1st floor.
  • Continued installation of Duxxbak decking.
  • Began installation of TPO roofing system.
  • Began applying stone veneer siding.

South Wing

  • Completed installation of 3rd floor joists and decking.
  • Began installation of 3rd floor wall panels.

Upper Level

  • Completed demolition work within formal dining room.
  • Completed demolition work within kitchen space.
  • Began framing soffits and ceilings in formal dining room.
  • Began MEP rough-ins in formal dining room.
  • Completed punchlist work at lounge, meeting room, and unisex bathroom.

New Connector

  • Completed priming and painting walls and soffits.
  • Completed laying brick veneer on exterior north side façade.
  • Completed installation of trim work including chair rail and handrail.
  • Began WCC pre-punchlist work.

10/20/2023: Work accomplished this week…

North Wing

  • Continued balcony framing and window installation around perimeter of building.
  • Completed installation of shingle roofing system.
  • Completed laying CMU columns at east canopy area.
  • Continued MEP rough-ins on all floors.
  • Began installation of patio doors.
  • Continue installation of Duxxbak decking.

South Wing

  • Completed setting structural steel.
  • Completed installation of 1st floor wall panels.
  • Completed installation of 2nd floor joists and decking.
  • Began installation of 2nd floor wall panels.

Upper Level –  Commons

  • Continued demolition work within formal dining room.
  • Continued demolition work within kitchen space.
  • Began wall and soffit layout in formal dining room.
  • Began WCC pre-punchlist work in lounge, meeting room, and unisex bathroom.

New Connector

  • Completed hanging and finishing drywall.
  • Completed laying custom carpet.
  • Completed MEP rough-in work.
  • Began priming and painting walls and soffits.
  • Began laying brick veneer on exterior façade.

10/13/2023: Work accomplished this week…
North Wing

  • Completed laying roof sheathing.
  • Continued balcony framing around perimeter of building.
  • Continued MEP rough-ins on first, second, third floors.
  • Continued installation of windows around perimeter of building.
  • Continued installation of shingle roofing system.
  • Began laying CMU columns at east canopy area.

South Wing

  • Prepared and placed concrete building pad.
  • Began setting structural steel.
  • Began installation of first floor wall panels.

Upper Level – Commons

  • Continued painting soffits along corridor.
  • Continued demolition work within formal dining room.
  • Began demolition work within kitchen space.
  • Set countertop within unisex bathroom and lounge area.

New Connector

  • Completed installation of windows and storefront.
  • Completed installation of roofing system.
  • Completed insulating walls and ceilings.
  • Began hanging and finishing drywall.
  • Continued installation of MEP rough-ins.
  • Applied waterproof membrane on exterior.

10/6/2023: Work accomplished this week…
North Wing

  • Completed setting roof trusses.
  • Continued laying roof sheathing.
  • Continued balcony framing around perimeter of building.
  • Continued MEP rough-ins on first, second, third floors.
  • Continued installation of windows around perimeter of building.
  • Completed laying CMU block for entry pavilion walls.
  • Completed setting stair tower metal door frames.
  • Begin installation of shingle roofing system.

South Wing

  • Completed underground plumbing.
  • Excavated for interior footers and haunches.

Commons

  • Completed prepping wall for paint application.
  • Continued priming and painting walls and soffits along corridor.
  • Completed removal of existing flooring along corridor and replacing it with new carpet/LVT.
  • Completed installation of unisex bathroom floor and= wall tile.
  • Installed casework within unisex bathroom.
  • Completed installing MEP finishes within unisex bathroom, lounge space, and meeting room 210.
  • Continued demolition work within formal dining room.
  • Completed framing walls and installing roof trusses and sheathing at new connector.
  • Began MEP rough-ins and installation of windows at new connector.

9/29/2023: Work accomplished this week…
North Wing

  • Continued setting roof trusses and sheathing.
  • Continued balcony framing around perimeter of building.
  • Continued MEP rough-ins on first and second floors.
  • Began MEP rough-ins on third floor.
  • Began installation of windows on west side of building
  • Began laying CMU block for entry pavilion walls.
  • Began setting stair tower metal door frames.

South Wing

  • Set steel column anchor plates in concrete footers.

Commons

  • Completed design team’s punchlist work in Bistro.
  • Continued removal of existing wallpaper along corridor and prepping wall for paint application.
  • Continued priming and painting walls and soffits along corridor.
  • Began removal of existing flooring along corridor and replacing it with new carpet/LVT.
  • Installed casework within lounge area.
  • Set unisex bathroom floor and wall tile.
  • Continued demolition work within formal dining room.
  • Completed laying CMU fire wall at new connector.
  • Began framing walls for new connector.

9/22/2023: Work accomplished this week…
North Wing

  • Continued setting roof trusses and sheathing.
  • Continued balcony framing along Bluebird Lane and south side of building.
  • Continued MEP rough-ins on first and second floors.
  • Continued hanging pre-rock along main corridor ceiling.
  • Prepped and placed first floor concrete patio floors.

South Wing

  • Completed installation of underground plumbing lines.

Commons

  • Items on order to complete design team’s punchlist work in Bistro.
  • Continued removal of existing wallpaper along corridor and prepping wall for paint application.
  • Continued priming and painting walls and soffits along corridor.
  • Prepped and placed concrete slab and began laying CMU fire wall at Bistro connector.
  • Completed hanging temporary walls around formal dining room.
  • Began demolition work within formal dining room.

9/15/2023: Work accomplished this week…
North Wing

  • Completed installation of fourth floor wall panels.
  • Begin setting of roof trusses.
  • Continued balcony framing along Bluebird Lane and south side of building.
  • Continued MEP rough-ins on first and second floors.
  • Completed framing and hanging vertical duct shaft linear outside of stair tower #2.
  • Continued hanging pre-rock along main corridor ceiling.
  • Began installation of exterior windows.

South Wing

  • Completed laying and grouting CMU foundation block.
  • Completed applying underground waterproofing system.

Upper Level – Commons

  • Items on order to complete design team’s punchlist work in Bistro.
  • Completed hanging and finishing drywall at unisex bathroom, lounge space and meeting room 210.
  • Began priming and painting walls in available spaces.
  • Completed MEP rough-ins at unisex bathroom, lounge spaces and meeting room 210.
  • Continued removal of existing wallpaper along main corridor and prepping wall for paint application.
  • Completed placing masonry foundation block, waterproofing and insulation for Bistro connector.

9/8/2023: Work accomplished this week…
North Wing

  • Continued installation of fourth floor wall panels.
  • Continued balcony framing along Bluebird Lane.
  • Began excavation for balcony foundations along south side of building.
  • Continued MEP rough-ins on first floor.
  • Began hanging pre-rock along main corridor ceiling.

South Wing

  • Completed excavation of west side perimeter foundation.
  • Placed concrete perimeter foundation and began laying masonry block along west side.

Lower Level – Commons

  • Passed Department of Health Inspection.

Upper Level – Commons

  • Continued design team’s punchlist work in Bistro.
  • Continued to hang and finish drywall at unisex bathroom/lounge spaces.
  • Continued MEP rough-ins at unisex bathroom/lounge spaces.
  • Began removal of existing wallpaper along main corridor and prepping wall for paint application.
  • Formed and placed Bistro connector foundation.
  • Began placing masonry foundation block for Bistro connector.

9/1/2023: Work accomplished this week…
North Wing

  • Completed installation of fourth floor joists and decking.
  • Began installation of fourth floor wall panels.
  • Continued balcony framing along Bluebird Lane.
  • Began MEP rough-ins on first floor.
  • Base paved west parking lot.
  • Prepped and place concrete for west side patio stairs and ramp.
  • Began hanging pre-rock in shower and tub openings.
  • Completed installation of storm line between structures A.6 and A.7.
  • Completed excavation of east side entrance way piers, installed rebar, and placed concrete.

South Wing

  • Completed demolition of south vaults, duct bank and deactivated underground utilities.

Lower Level – Commons

  • Completed start-up of kitchen equipment.

Upper Level –  Commons

  • Continued design team’s punchlist work in Bistro.
  • Completed framing and insulating walls and began hanging drywall at unisex bathroom/lounge spaces.
  • Continued MEP rough-ins at unisex bathroom/lounge spaces.
  • Completed demolition of existing link.

8/25/2023: Work accomplished this week…
North Wing

  • Completed installation of third floor wall panels.
  • Began installation of fourth floor joists.
  • Installed third floor structural steel.
  • Continued second floor wood framing punch work.
  • Continued balcony framing along Bluebird Lane.
  • Began layout for plumbing rough-ins.

South Wing

  • Continued demolition of south vaults, duct bank and deactivated underground utilities.
  • Placed concrete in metal pan stairs in stair tower #1.
  • Placed concrete pad in sprinkler room.

Lower Level – Commons

  • Completed start-up of mechanical equipment
  • Continue start-up of kitchen equipment.
  • Completed testing and balancing of equipment.

Upper Level – Commons

  • Continued design team’s punchlist work in Bistro.
  • Completed setting ceramic wall tile on pizza oven.
  • Set furniture within Fast Casual seating area and meeting room.
  • Began framing of walls and MEP rough-ins at unisex bathroom/lounge spaces.
  • Continued demolition of existing link.
  • Completed painting corridor 241 walls.

8/18/2023: Work accomplished this week…
North Wing

  • Completed installation of third floor decking.
  • Continue installation of third floor wall panels.
  • Completed first floor wood framing punch work.
  • Began second floor wood framing punch work.
  • Began first floor balcony framing.
  • Completed placing concrete curbing at west parking lot.
  • Connected building sanitary line into site sanitary line.

South Wing

  • Completed underground plumbing within sprinkler room.
  • Completed installation of new communication lines.
  • Began demolition of south vaults, duct bank and deactivated underground utilities.
  • Connect SSMH-4 into SSMH-3.
  • Framed stair tower #1 interior walls.

Lower Level – Commons

  • Completed design team’s punchlist work.
  • Continued start-up of kitchen/mechanical equipment.

Upper Level – Commons

  • Began design team’s punchlist work in Bistro.
  • Installed decorative metal at pizza oven.
  • Completed demolition work at future lounge/unisex bathroom spaces.
  • Began demolition of existing link.
  • Began painting corridor 241 walls.

8/11/2023: Work accomplished this week…
North Wing

  • Completed installing third floor wood joists.
  • Began installation of third floor decking.
  • Began installation of third floor wall panels.
  • Began first floor wood framing punch work.
  • Began placing concrete curbing at west parking lot.

South Wing

  • Continue installation of new communication lines.
  • Completed installing pan stairs at stair tower #1.
  • Began backfilling sprinkler room floor cavity.
  • Continue backfilling around south walls.

Lower Level – Commons

  • Continued architect punch list work.
  • Began start-up of kitchen/mechanical equipment.
  • Installed walk-off carpet and base in mechanical corridor.

Upper Level – Commons

  • Removed temporary walls at Bistro/Coffee Shop.
  • Installed temporary walls and began demolition at future lounge/unisex bathroom spaces.
  • Completed installation of new storefront doors in Bistro.
  • Completed final connections to food service equipment.
  • Began installation of decorative metal panels.

8/4/2023: Work accomplished this week…
North Wing

  • Completed installation of second floor wall panels.
  • Began installing third floor wood joists.
  • Removed forms and began backfilling at west patio ramp walls.
  • Installed temporary lighting along first floor corridor.

South Wing

  • Completed power switchover.
  • Continued installation of new communication lines.
  • Continued installing pan stairs at stair tower #1.
  • Poured remaining balance of south concrete walls.
  • Poured sprinkler room concrete walls.

Lower Level –  Commons

  • Complete architect punch list work.
  • Begin food service equipment start-up.
  • Test exhaust hood fire suppression system.

Upper Level – Commons

  • Demolish temporary mailroom.
  • Begin erecting temporary walls at future lounge/unisex bathroom spaces.
  • Complete installation of Bistro countertops and food= service equipment.
  • Complete MEP connections to food service equipment.
  • Install decorative metal around pizza oven.
  • Complete installation of new storefront doors in Bistro.

7/28/2023: Work accomplished this week…
North Wing

  • Completed installation of underground basin structure and associated storm structures.
  • Installed stormwater line across Blue Bird Lane adjacent to newly installed underground basin.
  • Completed installation of first floor wall panels and second floor joists.
  • Installed first floor structural steel.
  • Began installing second floor decking and wall panels.
  • Formed and poured west patio ramp walls.

South Wing

  • Continued running new communication and power lines.
  • Began installation of pan stairs in stair tower #1.

Lower Level – Commons

  • Continued architect punch list work.
  • Finished installing temporary breakers.
  • Installed ceiling grid and tile in service elevator lobby.

Upper Level – Commons

  • Began installing ceiling grid and tile in Bistro.
  • Continued installation of casework in Bistro.
  • Continued installation of food service equipment.
  • Completed punch list work in mailroom and removed temporary wall.
  • Began installation of MEP finishes in Bistro.

7/21/2023: Work accomplished this week…
North Wing

  • Continued installation of underground basin structure and associated storm structures.
  • Continued framing first floor walls.
  • Installed first floor structural steel.
  • Began placing wood joists and second floor decking.

South Wing

  • Continued running new communication and power lines.
  • Continued backfilling around south walls.

Lower Level – Commons

  • Continued architect punchlist work.
  • Continued installation of electrical panel breakers.
  • Installed epoxy flooring at service elevator lobby.
  • Installed vinyl flooring in mechanical corridor.

Upper Level – Commons

  • Installed carpeting in meeting room.
  • Installed wall covering and decorative light fixtures in Bistro and meeting room.
  • Continued installation of casework in Bistro and Coffee Shop.
  • Began installation of food service equipment in Bistro.
  • Completed installation of baseboard and began installing pilaster panels in Bistro.
  • Installed mailroom island casework.
  • Installed countertop in package room.

7/14/2023: Work accomplished this week…
North Wing

  • Placed stone at underground basin structure.
  • Placed west side concrete ramp and patio foundation.
  • Poured concrete in pan stairs in stair tower #2.
  • Began 1st floor wood wall framing.

South Wing

  • Continued running new communication and power lines.
  • Continued backfilling around south walls.
  • Completed installation of underground gas line.

Lower Level –  Commons

  • Continued architect punchlist work.
  • Continued installation of electrical panel breakers.
  • Installed FRP at service elevator landing.
  • Installed air hoods at walk-in coolers.

Upper Level – Commons

  • Completed installation of pantry casework.
  • Began installation of Grill and Coffee Shop casework.
  • Installed flooring in Coffee Shop area and corridor.
  • Continued installation of trim in Bistro and Coffee Shop.
  • Completed installation of trim in mailroom.
  • Began pilaster installation in mailroom.

7/7/2023: Work accomplished this week…
North Wing

  • Completed excavation work for underground basin and began installation of liner.
  • Completed excavation for west side patio foundation and placed concrete mud sill.
  • Framed interior center wall of stair tower #2.
  • Installed storm structure A.9 and continued excavation and associated piping to structure A.11.

South Wing

  • Continued running new communication and power lines.
  • Continued backfilling around south walls.

Lower Level – Commons

  • Continue architect punchlist work.
  • Completed installation of food service equipment.
  • Continue installation of electrical panel breakers.

Upper Level – Commons

  • Completed installation of wood baseboard and crown molding within mailroom.
  • Completed installation of crown molding at Coffee Shop ceiling.
  • Completed installation of flooring in package room.
  • Accepted delivery of pantry casework.

6/30/23: Work accomplished this week…
North Wing

  • Continued excavation work for underground basin.
  • Completed installing vapor barrier, rebar, and placing concrete building pad west of stair tower #2.
  • Placed concrete on steel decking at top of elevator and stair towers.
  • Graded and stoned east side parking lot.

South Wing

  • Continued running new communication and power lines.

Lower Level – Commons

  • Continue installation of electrical panels.
  • Continue installation of remaining food service equipment.
  • Began architect punchlist work.
  • Completed abatement work within maintenance corridor.

Upper Level – Commons

  • Completed installing exhaust duct to pizza oven and overhead exhaust hood.
  • Continued installation of stained wood trim and crown molding in mailroom and Coffee Shop area.
  • Installed ceiling grid and painted walls within package room.
  • Completed laying flooring within mailroom and Bistro area

6/22/2023: Work accomplished this week…
North Wing

  • Completed installation of metal stairs in stair tower #2.
  • Began installing storm structures on west side parking lot that are to connect into underground basin.
  • Completed laying masonry block for elevator tower #2.
  • Completed underground plumbing/electrical work west of elevator tower #2 and prepared area for slab pour.
  • Completed installation of metal decking atop of stair tower #2 and elevator towers #1 and #2.

South Wing

  • Placed concrete building pad south of elevator #1 to corridor 124.
  • Continued running new communication and power lines.

Lower Level – Commons

  • Continue installation of electrical panels.
  • Began installation of remaining food service equipment.
  • Continue Wohlsen pre-punchlist work.

Upper Level – Commons

  • Began installing exhaust duct to pizza oven and overhead exhaust hood.
  • Completed MEP finishes in Bistro seating area.
  • Completed installation of wood ceilings in Bistro and Coffee Shop area.
  • Began installation of stained wood trim and crown molding in mailroom.
  • Completed installation of MEP finishes in mailroom.

6/16/2023: Work accomplished this week…
North Wing

  • Continued installation of metal stairs in stair tower #2.
  • Continued preparation work for underground basin on west side of construction site.
  • Began laying masonry block for elevator tower #2.
  • Completed installation of conduit along Bluebird Lane for communication lines.

South Wing

  • Completed excavation and installation of underground plumbing lines and electrical/low voltage conduit.
  • Completed preparation work to pour building slab south of elevator tower #1 to corridor 124.
  • Completed east run of exterior masonry foundation.
  • Began running new communication lines.

Lower Level – Commons

  • Completed installation of outdoor mechanical equipment.
  • Continue installation of electrical panels and switchgear.
  • Began Wohlsen pre-punchlist work.

Upper Level – Commons

  • Completed installation of new rooftop units.
  • Continued MEP rough-ins in Bistro.
  • Continued MEP finishes in Bistro seating area.
  • Continued installation of wood ceilings in Bistro.
  • Completed installation of mailboxes.
  • Completed installation of ceiling grid within mailroom.
  • Began installation of MEP finishes in mailroom.
  • Completed installation of underground conduit under existing connector.

6/9/2023: Work accomplished this week…
North Wing

  • Completed installing vapor barrier and rebar for concrete building pad.
  • Poured concrete building pad east of stair tower #2.
  • Continued installation of metal stairs in stair tower #2.
  • Continued preparation work for underground basin on west side of construction site.

South Wing

  • Continue excavation and installation of underground plumbing lines and electrical/low voltage conduit.
  • Completed laying masonry block for stair tower #1.
  • Continue to backfill behind south foundation wall.

Lower Level-Commons

  • Continue installation of outdoor mechanical equipment.
  • Began installation of electrical panels and switchgear.

Upper Level-Commons

  • Continued MEP rough-ins in Bistro.
  • Continued MEP finishes in Bistro seating area.
  • Completed installation of ceiling grid in Bistro.
  • Completed hanging and finishing drywall in mailroom.
  • Completed painting work in IT closet and mailroom.
  • Continued installation of new rooftop units.
  • Began installation of wood ceilings in Bistro.
  • Began installation of mailboxes.

6/2/2023: Work accomplished this week…
North Wing

  • Continue installing vapor barrier in preparation of rebar install and placing of concrete building pad.
  • Began installation of building pad rebar.
  • Began installation of metal stairs in stair tower #2.
  • Began preparation work for underground basin on west side of construction site.

South Wing

  • Continue excavation and installation of underground plumbing.
  • Completed excavation and installation of sanitary sewer manholes and piping between SSMH 1 and SSMH-3.
  • Completed excavation and placing concrete for stair tower #1 foundation.
  • Began laying masonry block for stair tower #1.

Lower Level – Commons

  • Completed installing kitchen equipment.
  • Continued installation of outdoor mechanical equipment.

Upper Level – Commons

  • Continued MEP rough-ins in Bistro.
  • Began MEP finishes in Bistro seating area.
  • Began installation of ceiling grid in Bistro seating area.
  • Completed resinous flooring installation in Bistro.
  • Completed installation of windowsills in Bistro.
  • Continued hanging and finishing drywall in mailroom.
  • Completed MEP rough-ins in mailroom.
  • Began painting work in IT closet and mailroom.
  • Continued installation of new rooftop units.

5/26/2023: Work accomplished this week…
North Wing

  • Complete installation of building pad vapor barrier and interior footers/haunches rebar in preparation for placing concrete slab.
  • Begin installation of metal pan stairs in stair tower #2.

South Wing

  • Continue excavation and installation of underground plumbing.
  • Continue excavation and installation of sanitary sewer manhole and piping between SSMH-1 and SSMH-2.
  • Continue applying waterproofing membrane and perimeter underground insulation at newly placed foundation walls.
  • Begin forming and placing concrete foundation for stair tower #1.

Lower Level – Commons

  • Completed installation of MEP finishes.
  • Continue installing kitchen equipment.
  • Continue installation of outdoor mechanical equipment.

Upper Level – Commons

  • Continue MEP rough-ins.
  • Completed framing within mailroom.
  • Began hanging and finishing drywall in mailroom.
  • Continue MEP rough-ins in mailroom.
  • Began installation of new rooftop units.

5/19/2023: Work accomplished this week…
North Wing

  • Continue excavation for interior concrete footers, haunches and underground utility lines.
  • Continue installing underground plumbing lines.

South Wing

  • Complete excavation, installing rebar, and placing concrete for building foundation.
  • Began excavation and installation of electrical underground conduit.
  • Began masonry foundation work along west and east run of building.
  • Began applying waterproofing membrane, perimeter underground insulation and foundation drains at south foundation walls.

Lower Level – Commons

  • Continue installation of MEP finishes.
  • Began installing kitchen equipment.
  • Completed painting work within new electrical room.
  • Began installation of outdoor mechanical equipment.

Upper Level – Commons

  • Continue MEP rough-ins.
  • Completed insulating and hanging/finishing drywall within new IT Closet.
  • Began installation of ceiling grid.
  • Continue framing within mailroom.
  • Began MEP rough-ins in mailroom.

5/12/2023: Work accomplished this week…
North Wing

  • Continue excavation for interior concrete footers, haunches, and underground utility lines.
  • Continue installing underground plumbing lines and electrical conduit.

South Wing

  • Continue excavation, installing rebar, and placing concrete for building foundation.

Lower Level – Commons

  • Completed installation of ceiling grid.
  • Completed MEP rough-ins.
  • Began installation of MEP finishes.
  • Began installing perimeter ceiling tile.
  • Began painting work within new electrical room.

Upper Level – Commons

  • Continue MEP rough-ins.
  • Completed installing roofing system above new IT Closet.
  • Completed applying 1st coat of paint on drywall ceilings and walls.
  • Began framing walls within existing mailroom.

5/5/2023: Work accomplished this week…
North Wing

  • Continue excavation for interior concrete footers, haunches, and underground utility lines.
  • Continue installing underground plumbing lines and electrical conduit.
  • Completed excavation and installation of west side stormwater structures A.7 to A.9 and associated piping.

South Wing

  • Completed preparing building pad.
  • Completed forming and placing concrete for south foundation retaining wall.
  • Continue excavation, installing rebar, and placing concrete for building foundation.
  • Completed excavation and installation of water line to building.

Lower Level – Commons

  • Continue installation of ceiling grid.
  • Continue MEP rough-ins.
  • Completed hanging and finishing drywall in electrical room.
  • Began painting door frames.

Upper Level – Commons

  • Continue MEP rough-ins.
  • Completed hanging and finishing drywall soffits.
  • Completed installing wood trusses for new IT closet.
  • Continue replacing mechanical finishes in main corridor and lobby areas ceilings.
  • Began painting drywall ceilings and walls.
  • Completed demolition of existing mailroom.

4/28/2023: Work accomplished this week…
North Wing

  • Continue excavation for interior concrete footers, haunches, and underground plumbing lines.
  • Continue installing underground plumbing lines.
  • Began excavation and installation of west side stormwater structures and piping.
  • Began installing underground conduit for secondary electrical lines.

South Wing

  • Continue preparing building pad.
  • Continue excavation, installing rebar, and placing concrete for building foundation.

Lower Level

  • Began installation of ceiling grid.
  • Continue MEP rough-ins.
  • Completed new interior gas piping work.
  • Began hanging and finishing drywall in electrical room.

Upper Level

  • Continue MEP rough-ins.
  • Continue hanging and finishing drywall soffits.
  • Completed framing and sheathing for new IT closet.
  • Began installing wood trusses for new IT closet.
  • Continue replacing mechanical finishes in main corridor and lobby areas ceilings.
  • Relocated mailroom to temporary location.

4/21/2023: Work accomplished this week…
North Wing

  • Completed laying masonry walls at elevator #1.
  • Completed installing perimeter underground insulation, applying waterproofing membrane, and foundation drains.
  • Began excavation for interior concrete footers, haunches, and underground plumbing lines.
  • Began installing underground plumbing lines.

South Wing

  • Continue preparing building pad.
  • Began excavation, installing rebar, and placing concrete for building foundation.

Lower Level-Commons

  • Completed resinous flooring installation.
  • Continued new interior gas piping work.

Upper Level-Commons

  • Continued MEP rough-ins.
  • Completed framing soffits at coffee shop.
  • Continued hanging and finishing drywall.
  • Completed preparing former library space to be converted into a temporary mail room.
  • Began framing for new IT closet.
  • Began replacing mechanical finishes in main corridor and lobby areas ceilings.

4/14/2023: Work accomplished this week…

  • Continue preparing south wing building pad.
  • Completed masonry foundation work along south run of north wing of the building.
  • Completed laying masonry walls at elevator shaft #2.
  • Began laying masonry walls at elevator shaft #1.
  • Continue installing perimeter underground insulation, applying waterproofing membrane, and foundation drains around exterior of building.
  • Completed installing retaining wall railings.

Lower Level – Commons

  • Continued MEP rough-ins in kitchen.
  • Completed insulating mechanical ductwork.
  • Completed hanging FRP.
  • Continued new interior gas piping work.
  • Completed hanging fan coil units.

Upper Level – Commons

  • Continued MEP rough-ins.
  • Continued framing soffits.
  • Continued hanging and finishing drywall.
  • Formed and placed concrete slab on grade at connector.
  • Continued preparing former library space to be converted into a temporary mail room.

4/7/2023: Work accomplished this week…

  • Continue preparing south wing building pad.
  • Completed laying masonry walls at stair tower #2.
  • Continue masonry foundation work along south run of north wing of the building.
  • Began laying masonry walls at elevator shafts.
  • Began installing perimeter underground insulation, applying waterproofing membrane, and foundation drains around exterior of building.
  • Completed installing retaining wall.
  • Completed running primary underground electrical conduit.

Lower Level-Commons

  • Continued MEP rough-ins in kitchen.
  • Continued insulating mechanical ductwork.
  • Continued hanging FRP.
  • Continued new interior gas piping work.
  • Began hanging fan coil units.

Upper Level-Commons

  • Continued MEP rough-ins.
  • Continued framing soffits.
  • Continued hanging and finishing drywall.
  • Completed laying masonry foundation block, rigid insulation, and waterproofing at Bistro connector.
  • Completed running underground conduit to new IT closet.
  • Continued preparing former library space to be converted into a temporary mail room.

3/31/2023: Work accomplished this week…

  • Continue preparing south wing building pad.
  • Completed laying masonry foundation at stair tower #2 and along west, north, and east run of north wing of building.
  • Began laying masonry walls at stair tower #2.
  • Began masonry foundation work along south run of north wing of the building.
  • Began forming and placing concrete piers.
  • Completed installing rebar, forming walls, and placing concrete at elevator shafts.
  • Began applying waterproofing membrane around exterior of building and elevator shafts.
  • Continue installing retaining wall.
  • Continue running primary underground electrical conduit.

Lower Level-Commons

  • Continued Continued insulating mechanical ductwork.
  • Completed installing exhaust hoods and walk-in refrigerators.
  • Continued hanging FRP.
  • Began new interior gas piping work

Upper Level-Commons

  • Continued MEP rough-ins.
  • Continued hanging and finishing drywall.
  • Complete laying masonry foundation block at Bistro Connector.
  • Continued running underground conduit to new IT closet.
  • Began preparing former library space to be converted into a temporary mail room.

3/24/2023: Work accomplished this week…

  • Continue preparing south wing building pad.
  • Completed exterior concrete foundation work along north, east, and south run of north wing of building.
  • Began laying masonry foundation work at stair tower #2 and along north and west run of north wing of building.
  • Began installing rebar, forming walls, and placing concrete at elevator shafts.
  • Completed excavating and installing gas line for Commons Building.
  • Began installing retaining wall.
  • Began running primary underground electrical conduit.

Lower Level-Commons

  • Continued MEP rough-ins in kitchen & electrical room.
  • Continued insulating mechanical ductwork.
  • Completed exterior brick work.
  • Continued installing exhaust hoods and walk-in refrigerators.
  • Began hanging FRP.
  • Set new gas meter.

Upper Level-Commons

  • Continued MEP rough-ins.
  • Continued insulating and hanging drywall.
  • Completed installing wood clad windows.
  • Began laying masonry foundation block at Bistro Connector.
  • Continued running underground conduit to new IT closet.

3/17/2023: Work accomplished this week…

  • Completed installation of east side stormwater structure A.5 and associated piping to structure A.4.
  • Continue preparing site for building pad.
  • Began excavation, installing rebar, and placing concrete at exterior foundations along north side of building and at elevator #2 pit.
  • Began excavating and installing gas line for Commons Building.

Lower Level-Commons

  • Continued MEP rough-ins in kitchen & electrical room.
  • Continued insulating mechanical ductwork.
  • Continued exterior brick work.
  • Completed installing exterior siding at electrical room.
  • Completed installing kitchen exhaust fans.
  • Began installing exhaust hoods and walk-in refrigerators

Upper Level-Commons

  • Continued MEP rough-ins.
  • Began insulating and hanging drywall.
  • Began preparing openings for new window installation.
  • Began laying out masonry foundation block for connector.
  • Began running underground conduit to new IT closet.

3/10/2023: Work accomplished this week…

  • Completed installation of east side stormwater structures A.3 and A.4 and associated piping.
  • Began installation of east side stormwater structure A.5 and associated piping to structure A.4.
  • Continue preparing site for building pad.
  • Completed bulk excavation for new retaining wall.
  • Continue tying rebar in preparation for foundation work to begin.

Commons-Lower Level

  • Continued MEP rough-ins in kitchen & electrical room.
  • Continued insulating mechanical ductwork.
  • Continued insulating and hanging cement board.
  • Began exterior brick work.
  • Started installing kitchen exhaust fans
  • Placed concrete housekeeping pad for gas line.

Commons-Upper Level

  • Continued MEP rough ins.
  • Completed soffit and wall framing.
  • Completed excavation and placing concrete footers for Bistro connector.

3/3/2023: Work accomplished this week…

  • Continue installation of east side stormwater structures A.3 and A.4 and associated piping.
  • Connect to existing stormwater in Bluebird Lane.
  • Install wet tap to connect existing water line into new water line.
  • Continue preparing site for building pad.
  • Began bulk excavation for new retaining wall.
  • Began tying rebar in preparation for foundation work to begin.

Commons- Lower Level

  • Continued MEP rough-ins in kitchen & electrical room.
  • Began insulating mechanical ductwork.
  • Began insulating and hanging cement board.

Commons-Upper Level

  • Continued soffit and wall framing.
  • Continued MEP rough ins.
  • Continue excavation and placing concrete footers for Bistro connector.
  • Completed installing new flooring in Gift Shop.

2/17/2023: Work accomplished this week…

  • Completed removing parking lot blacktop.
  • Began installation of east side stormwater structures and piping.
  • Installed sanitary manhole 5 and piping to grease trap.
  • Continued MEP rough ins in kitchen & electrical room.
  • Began removing masonry block for new mechanical openings.
  • Installed steel lintels for new mechanical openings.
  • Began coring through upper floor deck for new floor drains.
  • Continued soffit and wall framing.
  • Continued MEP rough ins.
  • Completed shoring existing trusses for new openings to Bistro connector.
  • Continue underground rough ins for new IT closet.

2/10/2023: Work accomplished this week…

  • Completed stripping and stockpiling topsoil.
  • Continue removing parking lot blacktop.
  • Completed installing construction entrances.
  • Excavation of south wing deep foundation.
  • Scanning site for location of existing underground utilities.
  • Completed framing and wall blocking (in commons).
  • Completed installing roofing system at new electrical room addition (in commons).
  • Applied liquid vapor barrier at new electrical room.

1/27/2023: Work accomplished this week…

  • Continue MEP rough ins in DOH Kitchen.
  • Continue wall layout and framing in DOH Kitchen.
  • Completed roof trusses at new electrical room.
  • Began installing roofing system at new electrical room addition.
  • Excavated, installed, and backfilled new electrical vault for main service lines.
  • Began MEP rough ins in Bistro.

1/20/2023:Work accomplished this week…

  • Continue MEP rough ins in DOH Kitchen.
  • Continue wall layout and framing in DOH Kitchen.
  • Set roof trusses at new electrical room.
  • Completed underground rough-in in Bistro.
  • Continue demolition of exterior façade at Bistro.

1/6/2023: Work accomplished this week…

  • Completed saw cutting in Bistro Area.
  • Began removing concrete slab in Bistro Area.
  • Completed MEP demolition in Bistro Area
  • Prepped and placed concrete slab in new electrical room.
  • Began layout of MEP in DOH Kitchen.
  • Began wall layout and framing in DOH Kitchen.
  • Continued exterior excavation/installation of new underground electrical/telecom conduit.
  • Set grease trap.

12/30/2022: Work accomplished this week…

  • Continued MEP demolition in Bistro Area.
  • Started saw cutting in Bistro Area for new underground rough ins
  • Continued exterior excavation for new underground telecom lines
  • Poured concrete slab in DOH kitchen

12/22/2022: Work accomplished this week…

  • Began installing floor drains/troughs in lower level kitchen area (DOH kitchen).
  • Prep concrete slab in lower level kitchen area (DOH kitchen) and new electrical room.
  • Continue demolition in Bistro Area.
  • Continue exterior excavation for new underground telecom lines.
  • Completed trenching for new grease trap.

12/16/2022: Work accomplished this week…

  • Completed running conduit for new electrical services in DOH Kitchen.
  • Continued demolition in Bistro Area.
  • Began exterior excavation for new underground telecom lines.

10/17/2022: Construction has begun! We will post updates regularly, so check back here frequently to see what’s new!